Central Campus Construction

Williams Science Hall October 16 Update

Progress Update:

  • Building Access update – 2nd floor South entrance is closed 2 new, temporary, 1st floor entrances available.
    • 3rd floor East entrance with card access is unchanged (card reader is working)
    • Public elevators are operational!!!
  • 3rd Floor access to Central Stairwell is closing 10/15 for 3 weeks (CRA was 10/6)
  • 4th floor access to Central Stairwell will close for 4-6 hour window to abate the flooring and then reopened. The 3 week closure is cancelled at this time.
  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – slight delay awaiting a final valve.  Water will continue to be supplied.
  • Air Handler 2 – shutdown of existing and tie-in to new unit – Tentatively scheduled for 11/9; this work is anticipated to last 5 days just like we did for AHU1 – CRA pending.

Phase 1:

3rd & 4th Floors

  • Punch list items near completion
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).

1st & 2nd Floors

  • Glass railing system atrium stairs is onsite – installation almost complete!
  • Flooring installation is finalizing – Atrium stair area and main entrance remains
  • Above Ceiling and Electrical inspections complete
  • Room/door signage installation started, completion pending
  • Punch list walk by RDG 10/13
  • SFM walk for temp C of O – 10/8 – fire systems tested and space was approved to allow the elevators to be turned on and provide emergency exits through finished space. The exits are designated with cones, rope, barricades, and signage.

Phase 2:

  • Electrical demo and temp lighting is ongoing – focusing on 2nd and 3rd floors
  • Casework and full demo underway
  • Abatement of “black glue” beneath the flooring that was demoed will start week of 10/12
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started on North & South facades
  • Landscaping at main entrance – concrete planters poured and site cleared for paver installation

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy) – SFM walked, C of O is pending
  • Phase 2 4th floor on hold temporarily
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions – change orders
    • Freight Elevator
    • TC area
    • Equipment room – emergency power

Decisions or Resources Needed: Extensive review of the budget and anticipated spend is underway with extended construction schedule.

Williams Science Hall October 9 Update

Progress Update:

  • Building Access update – 2nd floor South entrance is closed 2 new, temporary, 1st floor entrances available.
    • 3rd floor East entrance with card access is unchanged (card reader is working)
    • Public elevators are operational!!!
  • 3rd Floor access to Central Stairwell is closing 10/15 for 3 weeks (CRA was 10/6)
  • 4th floor access to Central Stairwell will close for 4-6 hour window to abate the flooring and then reopened. The 3 week closure is cancelled at this time.
  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – slight delay awaiting a final valve.  Water will continue to be supplied.
  • Air Handler 2 – shutdown of existing and tie-in to new unit – Tentatively scheduled for 11/9; this work is anticipated to last 5 days just like we did for AHU1 – more info to come.

Phase 1:

3rd & 4th Floors

  • Punch list items near completion
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).

1st & 2nd Floors

  • Glass railing system atrium stairs is onsite – installation is progressing
  • Flooring installation is finalizing
  • Above Ceiling and Electrical inspections complete
  • Room/door signage installation started, completion pending
  • Punch list walk by RDG 10/13
  • SFM walk for temp C of O – 10/8 – fire systems tested and space was approved to allow the elevators to be turned on and provide emergency exits through finished space. The exits are designated with cones, rope, barricades, and signage.

Phase 2:

  • Electrical demo and temp lighting is ongoing – focusing on 2nd and 3rd floors
  • Casework and full demo underway
  • Abatement of “black glue” beneath the flooring that was demoed will start week of 10/12
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started on North facade
  • Landscaping at main entrance – frames for concrete planters

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy) – SFM walked, C of O is pending
  • Phase 2 4th floor on hold temporarily
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed: None at this time.

Williams Science Hall October 2 Update

Progress Update:

  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – 9/8 to 10/6
  • Air Handler 2 – 1 day shutdown for tie-in – this will be October/early November timeframe
  • Building Access update – 2nd floor South entrance is closing, 2 new, temporary, 1st floor entrances available. (See attached plans).
    • 3rd floor East entrance with card access is unchanged

Phase 1:

3rd & 4th Floors

  • Punch list items underway – due 10/5
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).
    • They are installing a “pan” that will allow the existing hood to operate in the new variable air flow system and, ultimately, complies with building code

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • Ceiling grid installed
  • Light fixtures installed
  • Flooring installation is finalizing
  • Above Ceiling and Electrical inspections to be complete
  • Room/door signage installation started, complete week of 10/5
  • Punch list walk by RDG 10/5
  • SFM walk for temp C of O – 10/8

Phase 2:

  • Waldinger removed both Bio Safety Cabinets from TC room; will remove fume hoods from 3005 and 4023
  • Electrical demo and temp lighting is ongoing
  • Corridor work and impact under review – CRA will be week of 10/5
  • Casework and full demo underway
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started
  • Landscaping at main entrance – frames for concrete planters
  • SW soffit is repaired and finished   

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • 11/6 – tentative Phase 2 4th floor North half to start
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
    • Walk occurred with Dr. Lyubchenko week this week
    • Meeting scheduled with Dr. Murry for 10/5
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed: None at this time.

Tissue culture casework ready for demo. The green is original to 1975.
Atrium feature wall – painted, before the new paneling was installed.

Williams Science Hall Update 9/25/20

Progress Update:

  • RO System Replacement in-progresswater will be supplied during this time
    • Estimated duration is 4 weeks – 9/8 to 10/6
  • Air Handler 2 – 1 day shutdown for tie-in – this will be October timeframe

Phase 1:

3rd & 4th Floors

  • SFM walked 3rd and 4th for the Official Temporary Certificate of Occupancy – fire panel / system was verified; a few penetrations in the 2 janitor’s closet and 1 in 1st floor electrical room have been addressed and photos submitted to SFM for approval and final C of O.
  • Punch list items underway – due 10/5
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).
    • They are installing a “pan” that will allow the existing hood to operate in the new variable air flow system and, ultimately, complies with building code

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • New doors and hardware installed
  • AV completed a site walk today  
  • Ceiling grid installed
  • Light fixtures installed
  • Flooring installation is finalizing
  • Above Ceiling and Electrical inspections to be complete week of 9/28

Phase 2: 4th  (South half) and 3rd floor temp walls are in place

  • Waldinger will decontaminate and remove Bio Safety Cabinets and fume hoods starting 9/28
  • TC Room emptied of equipment and Matheson/Helgett removed CO2 & nitrogen tanks
  • Electrical demo and temp lighting is ongoing
  • Corridor work and impact under review
  • Casework and full demo to start 9/28

Exterior:

  • EIFS work ongoing
  • Landscaping to start at main entrance 9/25   

Schedule

  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 10/1 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator
Williams Science Hall – Ground Floor Atrium Ceiling
Williams Science Hall – 3rd Floor Hallway

Questions? Contact Erin Peters

Williams Science Hall Update 9/18/20

Progress Update:

  • RO System Replacement in-progresswater will be supplied during this time
    • Estimated duration is 4 weeks – 9/8 to 10/6
  • Air Handler 2 – 1 day shutdown for tie-in – this will be October timeframe

3rd & 4th Floors

  • SFM walked 3rd and 4th for the Official Temporary Certificate of Occupancy – fire panel / system was verified; a few penetrations in the 2 janitor’s closet and 1 in 1st floor electrical room need to be addressed before final is issued.
  • Punch list items underway
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill). They are installing a “pan” that will allow the existing hood to operate in the new variable air flow system and, ultimately, complies with building code
  • Phase 2 occupant move – complete!
    • 4th floor copier moved from 4010 to 4.0.002 – any issues with printing at this new location, please reach out to IT
    • Break room on 4th off elevator lobby room 4.0.030A – Please do not use the sink at this time!
    • Conference room moved from 4010 to the new area to room 4.0.003

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • New door installation in progress on 2nd and 1st
  • Ceiling grid installed
  • Light fixtures installed
  • Flooring installation is finalizing

Phase 2: 4th  (South half) and 3rd floor temp walls are in place

  • Waldinger will decontaminate and remove Bio Safety Cabinets and fume hoods

Exterior:

  • EIFS work ongoing
    • The underside of the soffit on the Southwest corner is repaired and finish work is starting
  • Landscaping to start at main entrance 9/8 – delayed due to rain & mud   

Schedule

  • Pending  – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed:

  • Tissue Culture equipment status presently in the rooms
Williams Science Hall – 2nd Floor Elevator Lobby
Williams Science Hall – 1st Floor Auditorium

Questions? Contact Erin Peters.

Williams Science Hall Update

Progress Update:

  • RO System shutdown planned for Tuesday, 9/8water will be supplied during this time
    • 8 @ 5 gallon jugs were delivered; LCMS in route
    • Estimated duration is 4 weeks
  • Air Handler 2 – 1 day shutdown for tie-in – this will be October timeframe

3rd & 4th Floors

  • SFM scheduled for 9/14 @ 9am for Certificate of Occupancy walk (vacation all next week) – a preliminary walk occurred 8/24
  • 3rd and 4th floors are opening on a Conditional Temporary Certificate of Occupancy which allows us to move into the space prior to SFM walk
  • Punch list items underway
  • Phase 2 occupants moved 9/8-9/11 – almost complete
    • 4th floor copier moved from 4010 to 4.0.002
    • Break room on 4th off elevator lobby room 4.0.030A – Please do not use the sink at this time!
    • Conference room moved from 4010 to the new area to room 4.0.003

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • Concrete poured on 1st floor complete
  • New door installation in progress on 2nd and 1st
  • Ceiling grid installation – light fixtures to follow

Phase 2: 4th  (South half) and 3rd floor temp walls start 9/9 and 9/14

Other:

  • Any building issues, please contact Erin Peters prior to contacting Facilities.
  • Please report any elevator functional issues to Erin and she will reach out to O’Keefe

Exterior:

  • EIFS work ongoing –  major progress this past week
    • The underside of the soffit on the Southwest corner was demoed
  • Landscaping to start at main entrance 9/8 – delayed due to rain     

Schedule

  • 9/8 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/8 – relocations of Phase 2 occupants to start
  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; Erin will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed:

  • None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.

Questions? Contact Erin Peters

Williams Science Hall
Williams Science Hall

Williams Science Hall Update

Progress Update:

  • Air Handler 2 – delivery complete!
    • 1 day shutdown for tie-in – this will be October timeframe
  • RO System shutdown planned for Tuesday, 9/8water will be supplied during this time
    • 8 @ 5 gallon jugs were delivered; LCMS in route
    • Estimated duration is 4 weeks
  • Fire Panel Testing – Tuesday, 9/8, afternoon
    • Audible Alarms
    • Strobe testing

*Note: Fire Protection Services will make announcements prior to testing and after tests are complete. They will also announce emergencies during this time.

3rd & 4th Floors

  • SFM scheduled for 9/14 @ 9am for Certificate of Occupancy walk (vacation all next week) – a preliminary walk occurred 8/24
  • 3rd and 4th floors are opening on a Conditional Temporary Certificate of Occupancy which allows us to move into the space prior to SFM walk
  • Punch list items underway
  • Phase 2 occupants to start moving into Phase 1: 9/8-9/11
    • 4th floor copier, break room, and conference room moving down the hall on 9/11

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • Concrete poured on 2nd floor catwalk/lobby area
  • New door installation in progress on 2nd and 1st
  • Card reader rough-ins installed

Phase 2: 4th  (South half) and 3rd floor temp walls start 9/9 and 9/14

Other:

  • Any building issues, please contact me prior to contacting Facilities.
  • Please report any elevator functional issues to me and I will reach out to O’Keefe

Exterior:

  • EIFS work ongoing –  major progress this past week
    • The underside of the soffit on the Southwest corner was demoed
  • Landscaping to start at main entrance 9/8

Schedule

  • 9/8 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/8 – relocations of Phase 2 occupants to start
  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed:

  • None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.
Williams Science Hall
Williams Science Hall

Questions? Contact Erin Peters

Williams Science Hall Update

Progress Update: Not a lot of change from last week as we wrap up Phase 1 levels 3 and 4 for partial occupancy

  • Air Handler 2 – delivery schedule for September 1-2
    • Crane onsite on the East side of the building – 2 days
    • 1 day shutdown for tie-in – this will be October timeframe
  • Flooring installation complete on 3rd and 4th floors
  • Ceiling is installed on 3rd & 4th
  • Restroom tiling finishing on 1st floor; final fixture installation
  • New RO piping installed in Phase 1
    • RO System shutdown planned for Tuesday, 9/8 – water will be supplied during this time
    • Estimated duration is 4 weeks
  • Electrical and plumbing work is finalizing on 3rd and 4th; ongoing on 1st and 2nd  
  • HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
  • IT closets are all set – new switch installation starting today!
  • IT cabling is complete – awaiting termination
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
  • New door installation in progress on 2nd and 1st
  • Card reader rough-ins – need IT
  • Elevators and Elevator lobbies:
    • Interior finishes ordered
    • Floor leveler installation 8/31
  • Exterior:
  • EIFS work started on North and West facades 
    • The underside of the soffit on the Southwest corner was demoed
    • New glass installed with fritted pattern – almost complete

Schedule

  • 9/3 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/8 – relocations of Phase 2 occupants to start
  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
  • New IT closets activated / jack activation for Phase 1 occupants and transition in Phase 2
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed:

  • None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.

Williams Science Hall Update 8/21/20

Progress Update: Not a lot of change from last week as we wrap up Phase 1 levels 3 and 4 for partial occupancy

  • Domestic water shut-down – complete.
  • Air Handler 2 – delivery tentatively – September 1-2
    • Crane onsite on the East side of the building – 2 days
    • 1 day shutdown for tie-in – this will be October timeframe
  • Flooring installation 3rd floor in-progress
  • Ceiling grid installation – complete
    • Ceiling pads following final inspections
  • Final Above Ceiling Inspections for 3rd and 4th
  • Restroom tiling finishing on 1st floor; final fixture installation
  • New RO System & piping
  • Electrical and plumbing work is ongoing
  • HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
  • IT closets are being outfitted from top down – floor sealed, cabinets installed; UPSs, etc.
  • IT cabling is complete – awaiting termination
  • Glass walls on 3rd and 4th floors in atrium/elevator lobbies is complete
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
  • New doors are installed on 3rd and 4th; working on 2nd and 1st
  • Card reader rough-ins – need IT and power
  • Elevators and Elevator lobbies:
    • Interior finishes ordered
    • Floor leveler installation prior to tile
  • Exterior: No change this week.
    • EIFS work to continue all next week on North and West facades 
      • The underside of the soffit on the Southwest corner was demoed
    • New glass installed with fritted pattern – almost complete

Schedule

  • 8/28 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/2 – relocations of Phase 2 occupants to start
  • 9/7 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799
Williams Science Hall – New glass installed
Williams Science Hall – new glass installed

Questions? Contact Erin Peters

Williams Science Hall Weekly Update

Progress Update:

  • Reminder: Domestic water shut-down – Saturday, 8/15, 8am to 12pm (sinks, toilets, drinking fountains, eyewash stations, and decon showers)
  • Air Handler 2 – delivery and installation – pending new date (will be a Saturday)
    • CRA pending – 1 day shutdown for tie-in (same as delivery day)
    • Crane onsite on the East side of the building – 2 days
  • Brick paver demo on 1st and 2nd floors – complete. (South entrance at later date)
  • Flooring installation 3rd floor in-progress
  • Ceiling grid installation – complete
    • Ceiling pads following final inspections
  • Final Above Ceiling Inspections for 3rd and 4th
  • Restroom tiling finishing on 1st floor; fixture installation
  • New RO System & piping
  • Electrical and plumbing work is ongoing
  • HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
  • IT closets are being outfitted from top down – floor sealed, cabinets on campus for switches; UPSs, etc.
  • IT cabling is being installed
  • Glass walls on 3rd and 4th floors in atrium/elevator lobbies is almost complete
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
  • New doors are onsite – installation following the flooring
  • Card reader rough-ins
  • Casework installed! (see pics)
  • Elevators and Elevator lobbies:
    • The power to both passenger elevators was restored for contractor use. This will help reduce traffic in the occupied area and increase efficiency in the construction area
    • Interior finishes were approved and ordered
  • Exterior: No change this week.
    • EIFS work to resume 8/17 and continue all week on North and West facades 
      • The underside of the soffit on the Southwest corner to be replaced in its entirety
    • New glass installed with fritted pattern – almost complete

Schedule

  • 8/28 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/1 – relocations of Phase 2 occupants to start
  • 9/7 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 Insert the next upcoming project milestone(s) or major work – including GC and other services
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799