Central Campus Construction

Wittson/Wigton June 11 update

  • 42nd street will be closed on June 14 – 6pm to 2am.
    • A crane will be in the street to lift the Convergence sculpture up over the Poynter skywalk into the Northwall Plaza.
    • 42nd street will will be back open on June 15 at 2am.

Progress Update:

  • L8 North&West – Inspections on top of wall. Drywall top out 1 side.
  • L8 – Rare book room – Working on removal of south temp hvac unit and converting over to permanent unit.
  • L4 – Work around new Dunkin space, temp wall removal starts June 11. Hallway work south side. Touch ups in hallway intersection.
  • L4/L3 – Working on 42nd street vestibule, Door automatics in process. Electronics delay in auto operators/card readers.
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • AVISPL – Working on programming finishing touches.
  • Heritage – Working on Canopy, punchlist
  • Exterior –  complete.
  • Exterior – Northwall Plaza – lighting, benches, pavers, landscaping, irrigation system
  • Exterior – Emile Ramp – light bases, stucco, paint, wall lighting soon

Schedule:

  • L8 Library – touchups in common space rooms. Moving over to temp unit cooling next week.
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Coffee Cart – Tentative ETA on completion – June 23-30. Temp wall around coffee bar to be removed June 11
  • Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens.  CAST will have time to coordinate schedules before hallway closes.
  • Heritage Center Completion of audio visual – Substantially complete
  • Exterior – Northwall Plaza – dedication June 16
  • Heritage Center Grand Opening – June 29 (private event June 10)
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  

Wittson/Wigton May 28 update

Progress Update:

  • Construction closure of the Wittson-Bennett Skywalk starting May 21 and finishing June 4. The skywalk to Sorrell will be unaffected.
  • L8 North&West – Installation of HVAC duct in progress, framing, electrical
  • L8 – Rare book room – Working on removal of south temp hvac unit and converting over to permanent unit.
  • L5 – installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work touch ups
  • Wittson Hall – level 5 – power and data for 5025.
  • L4 – Dimensional Innovations (exhibit) work nearly complete. Exhibits are shrouded. Work around new Dunkin space. Hallway work south side.
  • Lab 4004. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, Door automatics in process. Medallion is installed.
  • Wittson Hall – Level 2 – finishing touches on CM breakroom.
  • AVISPL – Working on programming finishing touches.
  • Heritage – Working on Canopy, punchlist
  • Exterior – South Courtyard – working on sprinklers, lights, landscaping etc.
  • Exterior – Northwall Plaza – light pole bases, concrete stripes. Pavers and benches next week.   
  • Exterior – Emile Ramp – light bases start installing next week

Schedule:

  • L8 Library – Center section construction to be complete by June 1. South RBR unit to be operational by June 1.
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L7 – Wallpaper work starts June 1.
  • L6 staircase – TBD
  • L4 – Coffee Cart –Tentative ETA on completion –June 23-30. Temp wall around coffee bar to be removed approx. June 14
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • Wittson Hall – Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens. Hallway paint will start happening June 1.
  • Heritage Center Completion of audio visual – Substantially complete, minor programming edits ongoing. Done by June 9
  • Heritage Center Grand Opening – June 29 (private event June 10)
  • Exterior – South Courtyard – June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  

Wittson/Wigton May 21 update

Progress Update:

  • Contractors will be working this weekend to haul in soil to the Northwall Plaza, please be mindful of the working machinery. Machinery will be operating between Wittson and Poynter. (work plan attached)
  • Stair A will be closed on Saturday May 22. Welding work will be taking place from 7am to 1pm.(work plan attached)
  • Construction work on Wittson L3 near room 3044 will happen Saturday May 22. Work will be noisy.(work plan attached)
  • Construction closure of the Wittson-Bennett Skywalk starting May 21 and finishing June 4. The skywalk to Sorrell will be unaffected.(work plan attached)
  • L8 North&West – Installation of HVAC duct in progress
  • L8 – Rare book room – Working on connections of new HVAC unit in south room. Finishing window work in north room.
  • L5 –installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work complete
  • Wittson Hall – level 5 – power and data for 5025.
  • L4 – Dimensional Innovations (exhibit) work nearly complete. Exhibits are shrouded.
  • Lab 4004. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, Door automatics in process. Medallion is scheduled to be installed May 21 @ 3pm
  • Wittson Hall – Level 2 – finishing touches on CM breakroom
  • Wittson Hall – L2 – Lockers – Installing locker trims almost complete – 3 pieces need to be made to finish.
  • AVISPL – Working on programming finishing touches. Some panels on the new L4 theater screen are not working. Silicon Core is coming next week (from Japan) to trouble shoot.
  • University Tower L4 – new lock installed. Keyed X1.7. Security has access to lock and unlock for events in Heritage.
  • Heritage – Working on Canopy, punchlist
  • Exterior – South Courtyard – working on sprinklers, lights, landscaping etc.
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north. Sculpture foundation ready for new “Convergence” piece. Rain has delayed progress all week until today.
  • Exterior – Emile Ramp – light bases start installing next week

Schedule:

  • L8 Library – Center section construction to be complete by June 1. South RBR unit to be operational by June 1.
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L7 – Wallpaper to finish is on order, shipping from Japan, ETA May 24
  • L6 staircase – Laminate overlay close to starting May 8, waiting on laminate
  • L4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion –June 23-30. Temp wall around coffee bar to be removed approx. June 14
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 starting
  • Wittson Hall – Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens. Hallway paint will start happening June 1.
  • Heritage Center punchlist completion – May 30
  • Heritage Center Completion of audio visual – Ongoing, must be complete by June 1
  • Heritage Center Grand Opening – June 29 (private event June 10)
  • Exterior – South Courtyard –Landscaping complete May 18, June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  

Wittson/Wigton May 14 update

Progress Update:

  • Construction closure of the Wittson-Bennett Skywalk starting May 21 and finishing June 4. The skywalk to Sorrell will be unaffected.
  • L8 North – Demolition in progress.
  • L8 – Rare book room – Temp equipment is setup and holding steady, old equipment removal has started
  • L5 –installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work in progress.
  • Wittson Hall – level 5 – power and data for 5025 and working on wood paneling in 5027.
  • L4 – Dimensional Innovations (exhibit) work in progress.
  • Lab 4004 – Core Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, Door and hardware install in progress. Medallion is scheduled to be finished with production on May 11-12. Coordinating install with Chancellor’s team.
  • Wittson Hall – Level 2 – constructing ceiling, removing walls in old CM breakroom.
  • Wittson Hall – L2 – Lockers – Installing locker trims almost complete – 3 pieces need to be made to finish.
  • AVISPL – Working on programming finishing touches.
  • University Tower L4 – new core for door lock. Arrives soon. Keyed both sides
  • University Tower Exterior Restoration –South side in progress
  • Heritage – Working on Canopy, HVAC balancing, punchlist
  • Exterior – South Courtyard – working on grading, then sprinklers, lights, etc.
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north. Sculpture foundation ready for new “Convergence” piece.
  • Exterior – Emile Ramp – design checks in the works

Schedule:

  • L8 Library – Art Vault by Midwest Storage is scheduled for May 18
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L7 – Wallpaper to finish is on order, shipping from Japan, ETA May 24
  • L6 & McGoogan staircase – Wallpaper touch ups happening May 8-14. Stair work planned for laminate overlay close to starting May 8, waiting on laminate
  • L4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion –June 23-30.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • L3 Hospitalist PH 2 part 2 – Furniture starting May 12, 3044 moves to 3053 May 14.
  • Wittson Hall – Level 3 – South Hallway outside CAST – renovation approx. 2 weeks starting Mid-May after 42nd street vestibule opens.
  • Heritage Center punchlist completion – May 30
  • Heritage Center Completion of audio visual – May 15
  • Heritage Center Grand Opening – June 29
  • Exterior – South Courtyard –Landscaping complete May 18, June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Exterior – installation of plantings – May 20 depending on weather.
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule –
    • Budget –  

Wittson/Wigton May 7 update

Progress Update:

  • L4 Tile work outside Lab 4033/Hallway this weekend all weekend.
  • L8 North – Demolition in progress.
  • L8 – Rare book room – Temp equipment is setup and holding steady, old equipment removal has started
  • L5 –installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work in progress.
  • Wittson Hall – level 5 – power and data for 5025 and working on wood paneling in 5027.
  • L4 – Dimensional Innovations (exhibit) work in progress.
  • Lab 4004 – Core Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, Door and hardware install in progress. Medallion is scheduled to be finished with production on May 11-12. Coordinating install with Chancellor’s team.
  • Wittson Hall – Level 2 – constructing ceiling, removing walls in old CM breakroom.
  • Wittson Hall – L2 – Lockers – Installing locker trims almost complete – 3 pieces need to be made to finish.
  • AVISPL – Working on programming finishing touches.
  • University Tower L4 – new core for door lock. Arrives soon. Keyed both sides
  • University Tower Exterior Restoration –South side in progress
  • Heritage – Working on Canopy, HVAC balancing, punchlist
  • Exterior – South Courtyard – working on grading, then sprinklers, lights, etc.
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north. Sculpture foundation ready for new “Convergence” piece.
  • Exterior – Emile Ramp – design checks in the works

Schedule:

  • L8 Library – Art Vault by Midwest Storage is scheduled for May 18
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L7 – Wallpaper to finish is on order, shipping from Japan, ETA May 24
  • L6 & McGoogan staircase – Wallpaper touch ups happening May 8-14. Stair work planned for laminate overlay close to starting May 8, waiting on laminate
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion – Late June.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • L3 Hospitalist PH 2 part 2 – Furniture starting May 12, 3044 moves to 3053 May 14.
  • Wittson Hall – Level 3 – South Hallway outside CAST – renovation approx. 2 weeks starting Mid-May after 42nd street vestibule opens.
  • Heritage Center punchlist completion – May 30
  • Heritage Center Completion of audio visual – May 15
  • Heritage Center Grand Opening – June 29
  • Exterior – South Courtyard –Landscaping complete May 18, June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Exterior – installation of plantings – May 20 depending on weather.
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule –
    • Budget –  

Wittson/Wigton April 30 update

Progress Update:

  • Domestic water shutdown planned for May 6 from 1am to 7am. Please power down electron microscopes May 5 end of day. Hot and cold water will be out for this period of time (drinking water, sinks, toilets)
  • L8 North – Converting to construction space on May 3.
  • L8 – Rare book room HVAC equipment is on site. Coordination happening on setting up temp equipment, thermostat/humidistat location, monitoring.
  • L5 –installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work in progress.
  • Wittson Hall – level 5 – working on power and data for 5025. Once that is done working on wood paneling in 5027.
  • L4 – Dimensional Innovations (exhibit) work in progress.
  • Lab 4004 – Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, drywall finishing in progress.
  • L3 Hospitalist PH 2 part 2 – Data, punchlist.
  • Wittson Hall – Level 2 – constructing ceiling, removing walls in old CM breakroom.
  • Wittson Hall – L2 – Lockers – Installing locker trims almost complete – 3 pieces need to be made to finish.
  • AVISPL – Working on programming finishing touches.
  • University Tower L4 – new core for door lock. Arrives soon. Keyed both sides
  • University Tower Exterior Restoration –South side in progress – working on cleaning and coating old brick where it was previously below grade, continuing next week
  • Heritage – Working on Canopy, HVAC balancing, punchlist
  • Exterior – South Courtyard – working on sidewalk concrete, base for sculpture continues.
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north. Sculpture foundation continues.
  • Exterior – Emile Ramp – bids are under review. UNMC looking into procuring light poles

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending previous phase.  
  • L7 – Wallpaper to finish is on order, shipping from Japan, ETA May 24
  • L6 & McGoogan staircase – Wallpaper touch ups happening May 8-14. Stair work planned for laminate overlay May 8 to June 29.
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion – June.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • Wittson Hall – Level 3 – South Hallway outside CAST – renovation approx. 2 weeks starting Mid-May after 42nd street vestibule opens.
  • Wittson Hall – level 3 – Hospitalist phase 2 Part 2 – furniture after L5 moves take place
  • Heritage Center punchlist completion – May 20
  • Heritage Center Completion of audio visual – May 15
  • Heritage Center Grand Opening – June 29
  • Exterior – South Courtyard –Landscaping complete May 18, June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Exterior – installation of plantings – May 20 depending on weather.
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule –
    • Budget –  

Wittson/Wigton April 23 update

Progress Update:

  • Crane will be on site on April 29 to set Wittson rooftop units. Crane will set in south Heritage Courtyard
  • Domestic hot water will be out of service for 2 hours Tuesday April 27 from 5am to 7am.
  • L8 South (Library) – surplus work in progress.
  • L8 – Rare book room HVAC. Equipment submittals have been approved. Equipment is on order. ETA for equipment is Late April. Temp HVAC on site. Coordination happening on setting up temp equipment, thermostat/humidistat location, monitoring discussion.
  • L5 – Above ceiling work for new door in progress. Planning to start installation of new glass door & wall April 28. Dimensional Innovations (exhibit) work in progress.
  • Wittson Hall – level 5 – working on move sheets for reception
  • L4 – Dimensional Innovations (exhibit) work in progress.
  • Lab 4004 – Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, drywall finishing in progress.
  • L3 Hospitalist PH 2 part 2 – Data, punchlist.
  • Wittson Hall – Level 2 – constructing ceiling, removing walls in old CM breakroom.
  • Wittson Hall – L2 – Lockers – Installing locker trims almost complete – 3 pieces need to be made to finish.
  • AVISPL – Working on programming finishing touches. UNMC staff were trained on 4.23
  • University Tower L4 – new core for door lock. Arrives next week. Keyed both sides
  • University Tower L3– complete – furniture moving in.
  • University Tower Exterior Restoration –South side in progress – working on cleaning and coating old brick where it was previously below grade next week
  • Heritage – Working on Canopy, HVAC balancing, punchlist
  • Exterior – South Courtyard – working on sidewalk concrete, base for sculpture next week.
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north. Sculpture foundation starts next week.
  • Exterior – Emile Ramp – bids due on traffic control devices and lighting due next week.  

Schedule:

  • L8 South (Library) – Schedule dates. Moving items north to south April 17-21. Surplusing items in 8N starts April 22. Finishes the 29th.
  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending previous phase.  
  • L7 – Wallpaper to finish is on order, shipping from Japan, ETA May 24
  • L6 & McGoogan staircase – Wallpaper touch ups happening May 8-18. Stair work planned for May 8 to June 29
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion –  June.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • Wittson Hall – level 3 – Hospitalist phase 2 Part 2 – furniture in May after L5 moves take place
  • Heritage Center punchlist completion – May 15
  • Heritage Center Completion of audio visual – April 30
  • Heritage Center Grand Opening – June 29
  • Exterior – South Courtyard –Landscaping complete May 18, June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication TBD June 10-15
  • Exterior – installation of plantings – May 20 depending on weather.
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule –
    • Budget –  

Wittson/Wigton April 16 Update

Progress Update:

  • Heritage Center HVAC will be offline April 19 through April 21 to perform repairs. Ambient temperatures on those days are sufficient to accomplish this work.
  • Wittson Level 3 West restrooms will remain in service Saturday through April 17. East restrooms will be closed for construction work happening on the floor above.
  • Level 4 – Work taking place in ceiling near service elevator. Elevator still in service for deliveries.
  • L8 South (Library) – moving in progress
  • L8 – Rare book room HVAC. Equipment submittals have been approved. Equipment is on order. ETA for equipment is April 15-22nd. Temp HVAC on site. Working through issues related to dust in RBRs
  • L7 – Wallpaper to finish is on order
  • L6 & McGoogan staircase – Wallpaper touch ups happening May 8-18. Coordination on upcoming laminate work at staircase.
  • L5 – Above ceiling work for new door in progress. Planning to start installation of new glass door & wall in late April. Dimensional Innovations (exhibit) work in progress.
  • Office 5020 and 5021 Moving in on Mon/Tues
  • L4 – Dimensional Innovations (exhibit) work in progress.
  • Lab 4004 – Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, interior framing in progress.
  • L3 Hospitalist PH 2 part 2 – Data, punchlist.
  • Wittson Hall – Level 2 – constructing ceiling, removing walls in old CM breakroom.
  • AVISPL – Working on site this week and next. Next step is functionality training near the end of April
  • University Tower L4 – temp 2×4’s in place for wood door, permanent lock should arrive in Omaha today, then core will be installed.
  • University Tower L3– open to traffic. Working inside conference 3130, duct, soffits, ceiling.
  • University Tower Exterior Restoration –South side started
  • Heritage – Working on Canopy, HVAC balancing, punchlist
  • Exterior – South Courtyard – working on sidewalk concrete
  • Exterior – Northwall Plaza – hardscape foundations, light pole bases, sidewalk, working from south to north.
  • Exterior – Emile Ramp –designs work on traffic control device and lighting. Signage approved and moving forward  

Schedule:

  • L8 South (Library) – Schedule dates. Moving items north to south April 17-21. Surplusing items in 8N starts April 22.
  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending previous phase.  
  • Wittson Hall – level 5 – 1-3 people moving April 19
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion – June.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • Wittson Hall – level 3 – Hospitalist phase 2 Part 2 – move in April.
  • Wittson Hall – L2 – Lockers – Installing locker trims the week of April 19
  • Heritage Center furniture install phase will continue
  • Heritage Center punchlist completion – May 15
  • Heritage Center Completion of audio visual – April 30
  • Heritage Center Grand Opening – TBD
  • Exterior – South Courtyard – Sidewalks April 16, Landscaping complete May 18, June 1 Sculpture base installation, Dedication June 10
  • Exterior – Northwall Plaza – TBD
  • Exterior – installation of plantings – May 1 depending on weather.
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule –
    • Budget – no contingency left.

Wittson/Wigton April 9 Update

Progress Update:

  • Wittson Level 3 West restrooms will remain in service Saturday through April 17. East restrooms will be closed for construction work happening on the floor above.
  • Level 4 – Work taking place in ceiling near service elevator. Elevator still in service for deliveries.
  • L8 South (Library) – Shelving work finished up this week. Working on hallway ceilings, drywall, lighting, toilet partitions next week.
  • L8 – Rare book room HVAC. Equipment submittals have been approved. Equipment is on order. ETA for equipment is April 15-22nd. The first step will be setting up temp hvac equipment so the old equipment can be removed. CRA setup for Monday.
  • L7, Finishing wall flattening work in E->W hallway. Wallpaper to finish is on order
  • L6 & McGoogan staircase –Wallpaper touch ups happening May 8-18. Coordination on upcoming laminate work at staircase.
  • L5 – Above ceiling work for new door starts 4-9. Planning to start installation of new glass door & wall in late April/early May.. Dimensional Innovations (exhibit) work starting 4-9.
  • L4 – Dimensional Innovations (exhibit) work starting 4-12
  • Lab 4004 – Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, interior framing in progress.
  • L3 – Hospitalist PH2 part 1 – Moving forward with adding a wall mounted screen.
  • L3 Hospitalist PH 2 part 2 – Data, punchlist.
  • Wittson Hall – Level 2 – computer moved, working with CM on start date
  • AVISPL – Returning on April 13 to continue L4 & L5 screens
  • University Tower L3– open to traffic. Working inside conference 3130, duct, soffits, ceiling
  • University Tower Exterior Restoration –South side started
  • Heritage – Working on Canopy, HVAC balancing, punchlist.
  • Exterior – South Courtyard – working on sidewalk concrete.
  • Exterior – Northwall Plaza – Still working on sub grade drainage, hardscape foundations
  • Exterior – Emile Ramp –designs work on traffic control device and lighting.  

Schedule:

  • L8 South (Library) – Work to be completed the week of April 12 – (furniture)
    • Schedule dates. Furniture April 5-17. Moving items north to south April 17-21. Surplusing items in 8N starts April 22.
  • Wittson Hall – Level 8 Hallway between elevator and library. Goal is to have this area walkable and dust free by April 15. Work to be completed the week of April 12 – lighting, inspections, ceiling pads.
  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending previous phase.  
  • Wittson Hall – level 5 – potential move April 19
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion – June.
  • Wittson Hall – Level 4 –  
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • Wittson Hall – level 3 – Hospitalist phase 2 Part 2 – move in April.
  • Wittson Hall – L2 – Lockers – Installing locker trims the week of April 19
  • Heritage Center furniture install phase will continue
  • Heritage Center punchlist completion – May 15
  • Heritage Center Completion of audio visual – April 30
  • Heritage Center Grand Opening – TBD
  • Exterior – South Courtyard – TBD
  • Exterior – Northwall Plaza – TBD
  • Exterior – installation of plantings – May 1 depending on weather. Budget Status:
  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – North courtyard and south sculpture are a rush to get completed in time.
    • Budget – no contingency left.

Wittson/Wigton April 2 Update

Progress Update:

  • Wittson Level 4 – Labs 4033, 4037, 4038 will be unavailable April 2-4 for abatement work. Wittson-> Sorrell and Wittson -> Bennett SKYWALKS WILL BE CLOSED due to hallway abatement
    • Highlighted plan sent out last week showing affected area.
  • Level 4 – Work taking place in ceiling near service elevator. Elevator still in service for deliveries.
  • L8 South (Library) – Moved
  • L8 – Rare book room HVAC. Equipment submittals have been approved. Equipment is on order. ETA for equipment is April 15-22nd.
  • L7, Finishing wall flattening work in E->W hallway. Wallpaper to finish is on order
  • L6 & McGoogan staircase –Wallpaper touch ups happening May 8-18. Coordination on upcoming laminate work at staircase.
  • L5 – Demo for the glass wall is complete. Podium delivered.
  • L4 – Open for traffic east and west through Heritage Center and Wittson.
  • Lab 4004 – Working on installation of suspension system. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, interior framing in progress.
  • L3 Center Stair. Open for traffic – painting work will happen this weekend.
  • L3 – Hospitalist PH2 part 1 – Moving forward with adding a wall mounted screen.
  • L3 Hospitalist PH 2 part 2 – Data, punchlist.
  • Wittson Hall – Level 2 –2 activations for more data so computer can move for Comp Med.
  • Dimensional Innovations – Will be on L5 starting April 8.
  • AVISPL – Returning on April 13 to continue L4 & L5 screens
  • University Tower L3– open to traffic. Working inside conference 3130, hallway is complete.
  • University Tower Exterior Restoration –South side started
  • Heritage – Working on Canopy, HVAC balancing, punchlist.
  • Exterior – South Courtyard – Paving poured yesterday – next work to do is installing sidewalk concrete.
  • Exterior – Northwall Plaza – Still working on sub grade drainage.  
  • Exterior – Emile Ramp – prelim designs continuing on traffic control device and lighting.  

Schedule:

  • L8 South (Library) – Work to be completed the week of April 5 – (finishing shelves, installing card access)
    • Schedule dates. Furniture April 5-17. Moving items north to south April 17-21. Surplusing items in 8N starts April 22.
  • Wittson Hall – Level 8 Hallway between elevator and library. Goal is to have this area walkable and dust free by April 15. Work to be completed the week of April 5 – ceiling framing, lighting, inspections, ceiling pads.
  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending previous phase.  
  • Wittson Hall – level 5 – potential move April 19
  • Wittson Hall – level 4 – Coffee Cart – Dunkin is working on final construction plans. Tentative ETA on completion – June.
  • Wittson Hall – Level 4 – Skywalks will be out of service – see notes at top of page 1.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction until Mid-May.
  • Wittson Hall – level 3 – Hospitalist phase 2 Part 2 – move in April.
  • Wittson Hall – L2 – Lockers – Installing locker trims the week of April 19
  • Heritage Center furniture install phase will continue
  • Heritage Center punchlist completion – April 30
  • Heritage Center Completion of audio visual – April 30
  • Heritage Center Grand Opening – TBD
  • Exterior – South Courtyard – TBD
  • Exterior – Northwall Plaza – TBD
  • Exterior – installation of plantings – May 1 depending on weather. Sculpture following.

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – North courtyard and south sculpture are a rush to get completed in time.
    • Budget – no contingency left.