Central Campus Construction

Wittson/Wigton September 17 Update

Progress Update:

  • Service Elevator – offline for new improvements – October 7-10th
  • L8 North&West – installation of furniture and phone cabling continuing
  • L5 – looking at carpeting outside of office 5030
  • L3 – gathering cost to upgrade door in Heritage hallway to card access

Schedule:

  • L8 – NM Pulmonary space – Move-in starting October 10
  • L6 staircase – Laminate work starting 12-16-21
  • L3 – replacement furniture for Rheum – early and mid October delivery
  • North Plaza – Screen wall work starts mid October

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton August 27 Update

Progress Update:

  • L8 North&West – move out materials, touch ups, doors&hardware
  • L4 – wall guard installation taking place outside labs 4033, 4037, 4038.
  • L3 – Punch list items, wall guard installation – to be complete Aug 30
  • Bennett Ramp – installing traffic device and clearance bar. Will be complete by Aug 30
  • North plaza – grading work for rock area continues

Schedule:

  • L8 – NM Pulmonary space – September 1 furniture start. Move-in late Sept.
  • L6 staircase – Laminate work starting 12-16-21
  • L5 – moving furniture, installing carpet on Sept 3-5
  • L4 –hallway work to be complete by Sept 7
  • L4 – carpet work on north hallway on 8-28-21
  • North Plaza – Screen wall work starts 9-3-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton August 20 Update

Progress Update:

  • L8 North&West – move out materials, touch ups, doors&hardware
  • L4 – wall guard installation taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L3 – Punch list items, wall guard installation – to be complete Aug 30
  • Bennett Ramp – installing traffic device and clearance bar. Will be complete by Aug 30

Schedule:

  • L8 – NM Pulmonary space – September 1 furniture start. Move-in late Sept.
  • L6 staircase – Laminate work starting 12-16-21
  • L5 – moving furniture, installing carpet on Sept 3-5
  • L5 – coordinating dates for carpet replacement with L5 offices
  • L4 –hallway work to be complete by Aug 30
  • L4 – carpet work on north hallway on 8-28-21
  • Northwall – minor work in river rock area on Aug 20. Inlet work starting Aug 16.

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittons/Wigton August 13 Update

Progress Update:

  • L8 North&West – Inspections, Ceiling pads, Electrical, Lighting, Paint, Carpet, Doors&HW
  • L6 – Work in Stair A (drywall) – painting
  • L5 Continuing work on door replacements at stairwells
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4 – working on door replacement at Sorrell skywalk – skywalk will remain open Monday through Friday – Skywalk will be closed Saturdays Aug 14
  • L4/L3 – Punch list items, wall guard installation – to be complete Aug 30
  • Exterior – Emile Ramp – lighting along wall will continue through next week.
  • Bennett Ramp – installing traffic device and clearance bar. Will be complete by Aug 30

Schedule:

  • L8 – NM Pulmonary space – September 1 furniture start. Move-in late Sept.
  • L6 staircase – Laminate work starting 12-16-2021
  • L5 – moving furniture, installing carpet on Aug 27 and Sept 3
  • L5 – coordinating dates for carpet replacement with L5 offices
  • L5 – moving furniture pieces etc. 5030 to 5027 and 3044 on 8-10-21.
  • L4 – door and hallway work to be complete by Aug 30
  • Northwall – minor work in river rock area on Aug 20. Inlet work starting Aug 16.

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton August 6 Update

Progress Update:

  • L8 North&West – Inspections, Ceiling pads, Electrical, Lighting, Paint, Carpet, Doors&HW
  • L6 – Work in Stair A (drywall) – from existing sprinkler leak
  • L5 Continuing work on door replacements at stairwells
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4 – working on door replacement at Sorrell skywalk – skywalk will remain open Monday through Friday – Skywalk will be closed Saturdays Aug 14
  • L4/L3 – Punch list items, wall guard installation
  • Exterior – Emile Ramp – lighting along wall will continue through next week.

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – Laminate work starting 12-16-2021
  • L5 – coordinating dates for carpet replacement with L5 offices
  • L5 – moving furniture pieces etc. 5030 to 5027 and 3044 on 8-10-21.

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton July 30 Update

  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades 7-26 to 8-3. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Ceiling pads, Electrical, Lighting, Paint, Carpet, Doors&HW
  • L6 – Work in Stair A (drywall) – from existing sprinkler leak
  • L5 Continuing work on door replacements at stairwells
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4/L3 – Punch list items, wall guard installation
  • Exterior – Emile Ramp – lighting along wall starting 7-26 – will continue through next week.

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – Laminate work starting 12-16-2021
  • L5 – coordinating dates for carpet replacement with L5 offices

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton July 23 Update

  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades the week of 7-26. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting, Paint, Carpet
  • L6 – Work in Stair A to repair existing fire sprinkler system drain lines.
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4/L3 – Punch list items, wall guard installation
  • L3 Hospitalist PH 2 part 3 – complete
  • Level 3 – south hallway work outside CAST – complete
  • Exterior – Emile Ramp – lighting along wall starting 7-26

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – Laminate is here. Coordinating a start date. 5-8 week install process.
  • L5 – Starting work on Door replacements at N and S stairways on L5 on Saturday July 24

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton July 16 Update

  • Bennett Hall exterior drive will be out of service for construction Sunday July 18 from 6am to 4pm for work related to traffic control system.
  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades the week of 7-19. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting, Paint, Carpet
  • L8 – Rare book room (north) – Complete
  • L6 – Work in Stair A to repair existing fire sprinkler system drain lines.
  • L4/L3 – Punch list items
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 punchlist
  • Level 3 – south hallway work outside CAST – working on touch ups
  • Exterior – Emile Ramp – lighting along wall starting next week.

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – TBD based on laminate delivery.  
  • L5 – Starting work on Door replacements at N and S stairways on L5 on Saturday July 24
  • L4 – Dunkin – Opening date for selling coffee is around July 22.
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Wittson/Wigton July 2 Update

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting
  • L8 – Rare book room (north) – Working on insulation, completion of the North RBR mech room. Still some programming and controls work to do on these units.
  • L6 – starting work soon on Stair A to repair old sprinkler system drain.
  • L4/L3 – Punch list items
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • Level 3 – Started south hallway work outside CAST    
  • Heritage – Working on Canopy
  • Exterior – Northwall Plaza – lighting, benches,  
  • Exterior – Emile Ramp – lighting along wall.

Schedule:

  • L8 Library – RBR hvac finishing soon
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Dunkin – Opening date for selling coffee is around July 7.
  • L4 – Work around new Dunkin space is 99% complete. Date of open sales is between July 7-12.
  • L3 – hallway work outside CAST – completion approx. July 14
  • Bennett Ramp – traffic control device work starts tomorrow (Saturday) – for a few hours the ramp will be obstructed while loop sensors are installed.
  • Heritage Center Completion of audio visual – Substantially complete
  • Heritage Center Grand Opening – June 29 
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  

Wittson/Wigton June 25 update

Progress Update:

  • L8 North&West – Inspections on top of wall. Drywall top out 1 side.
  • L8 – Rare book room (north) – Working on installation of new hvac unit.
  • L4 – Work around new Dunkin space is 99% complete. Date of open sales is TBD.
  • L4/L3 – Working on 42nd street vestibule touch ups
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • L2 – cleanup/punchlist.
  • Heritage – Working on Canopy,  
  • Exterior – Northwall Plaza – lighting, benches,  
  • Exterior – Emile Ramp – lighting along wall.

Schedule:

  • L8 Library – RBR hvac finishing soon
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Coffee Cart – Tentative ETA on completion – June 30.  
  • Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens (Starting June 30th – 2 week duration).  
  • Heritage Center Completion of audio visual – Substantially complete
  • Heritage Center Grand Opening – June 29 
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –