Wittson/Heritage Center Update November 20

Progress Update:

  • WATER OUTAGE – Nov 24th starting at 6pm ending on Nov 25th and 6am.
  • Level 8 – abatement complete, Construction starting. Center wall was removed due to asbestos. UNMC/HCI working on removing 2 adjacent room walls which will allow more open/large space.
  • L8 Rare book room HVAC. Drawings are at 100% stage from SES. Given to contractors. Recurring coordination has been setup with the contractors. Equipment Q &A is being worked through.
  • L7, L6 – Punchlist, Furniture, McGoogan staircase construction ongoing, punch list walk complete. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Mechanical and electrical rough-ins continue. Sheeting walls with Drywall.
  • Wittson Hall – Level 4 – Closed for construction on main east west hall. Working on 42nd street vestibule (exterior wall is removed). Relocations in progress for MEP on areas where floor is to be removed.
  • Lab 4004 Constructing new HVAC and Electrical, ceilings, lighting. Casework is now installed.
  • L4 working on west side construction of new connection point to heritage. MEP work,  ceiling framing.
  • L4 – Conference 4013 –AV install is scheduled for starting the 24th.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Work pending pricing for CPR 65. CPR 65 incorporates needs for Dimensional Innovations.
  • L3 working on ceilings/paint/flooring in Hospitalist PH2 part 1. Phase 2 part 2 working on framing this week. Masonry next week.
  • L2 Punchlist work in progress on locker rooms. L2 family RR and CM breakroom working on plumbing, electrical.
  • L2 Sterilizer. Installation of sterilizer in progress. Met with Primus/Spire regarding needs for electrical last week. Main Electrical components are complete. The bulk of the work left to do is by Primus-Spire.
  • Dimensional Innovations – Working through exact needs and coordination with construction – ongoing.
  • AVISPL – Could not meet in person because of COVID/travel issues AVISPL is having in their office.
  • University Tower L3-L6 – working on terra cotta façade and windows, mechanical, electrical, framing, demo, flooring, cleanup. Some windows were mis-measured by contractors and are being re-ordered, still no ETA on those. Level 6 walk through scheduled for Nov 30.
  • University Tower L3 hallway – this was recently renovated to the west of the construction zone. Per current plans, the hallway inside the construction zone does not get finished. Working on a pricing to match UT1 hallway.
  • University Tower – east façade restoration work continues. Users please keep windows closed. Signs are posted.
  • Heritage, currently installing mechanical and electrical. Focusing on high ceiling work first. (Perforated drywall, lighting).
  • Exterior – Northwall Plaza – rebar is ready for artwork foundations
  • Exterior – South Courtyard – working on retaining walls

Schedule

  • Wittson Hall – level 8 south (library collections) –tentatively furniture start late February. Move in Mar.
  • Wittson Hall – level 8 Neb Med space – July/Aug 21’ – pending multiple phases.  
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in Late January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) until Feb.
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected.  
  • Wittson Hall – level 4 – Lab 4004. Completion in late December, furniture in January.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Mar.
  • Wittson Hall – level 3 – Hospitalist project phase 2 part 1, furniture install in December, opening late December. Part 2 – Furniture in January, move in Feb early.
  • Wittson Hall – level 3 elevator lobby construction –December 18 to Feb 1
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Dec 18 to Feb
  • Wittson Hall – Level 2 – Family RR and CM breakroom complete in late Nov. Will move computer to breakroom shortly after.
  • Wittson Hall – main center staircase closed for construction – Now until Feb
  • Heritage Center furniture install starts mid-February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – April 2021
  • Heritage Center Completion of exhibits and audio visual – April 2021
  • Heritage Center Grand Opening – Late May 2021
  • University Tower – Levels 3-6 – Some areas will be ready for furniture after Thanksgiving.
  • Exterior – South Courtyard – Completion date coincides with Heritage.
  • Exterior – Northwall Plaza – completion late May 2021
  • Exterior – installation of plantings – likely April/May 2021 depending on weather for North and South Courtyard.  

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been hot and cold with construction workers but still an issue. Workers are now being monitored over lunchtime for proper separation.
    • Quality – punchlist timeliness has been an issue   
    • Schedule – Many areas have work happening. Covid has been an issue more and more it seems as the year goes on.
    • Budget – no contingency left.

Wittson/Wigton Project Update November 13

Progress Update:

  • Level 8 – abatement complete, Construction starting. Center wall was removed due to asbestos. UNMC/HCI working on removing 2 adjacent room walls which will allow more open/large space.
  • L8 Rare book room HVAC. Drawings are at 100% stage from SES. Given to contractors. Recurring coordination has been setup with the contractors.
  • L7, L6 – Punchlist, Furniture, McGoogan staircase construction ongoing, punch list walk complete. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Mechanical and electrical rough-ins continue. Topping out Drywall.
  • Wittson Hall – Level 4 – Closed for construction on main east west hall. Working on 42nd street vestibule (exterior wall is removed). Relocations in progress for MEP on areas where floor is to be removed.
  • Lab 4004 Constructing new HVAC and Electrical, ceilings, lighting. Casework is now installed.
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L4 – Conference 4013 – working on cabling and jack activation. AV install is next step.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Work pending pricing for CPR 65. CPR 65 incorporates needs for Dimensional Innovations.
  • L3 working on ceilings/paint/flooring in Hospitalist PH2 part 1. Phase 2 part 2 working on framing this week. Masonry next week.
  • L2 working on locker rooms, touchup and small items. Punchlist walkthrough scheduled for next Thursday. L2 family RR walk through week of Nov 23
  • L2 Sterilizer. Installation of sterilizer in progress. Met with Primus/Spire regarding needs for electrical last week. Main Electrical components are complete. The bulk of the work left to do is by Primus-Spire.
  • Dimensional Innovations – Working through exact needs and coordination with construction – ongoing.
  • AVISPL – We met on Nov 12 to discuss low voltage/conduit/cabling needs. We have a 2nd walk scheduled on Nov 16 to review pipe, wiring and data.
  • University Tower L3-L6 – working on terra cotta façade and windows, mechanical, electrical, framing, demo, flooring, cleanup. Some windows were mis-measured by contractors and are being re-ordered, still no ETA on those.
  • University Tower L3 hallway – this was recently renovated to the west of the construction zone. Per current plans, the hallway inside the construction zone does not get finished. Working on a pricing to match UT1 hallway.
  • University Tower – east façade restoration work continues. Users please keep windows closed. Signs are posted.
  • Heritage, currently installing mechanical and electrical. Focusing on high ceiling work first. (Perforated drywall, lighting).
  • Exterior – Northwall Plaza – rebar being procured for artwork foundations
  • Exterior – South Courtyard – working on retaining walls

Schedule

  • Wittson Hall – level 8 south (library collections) –tentatively furniture start late February. Move in Feb/Mar.
  • Wittson Hall – level 8 Neb Med space – July/Aug 21’ – pending multiple phases.  
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in Late January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) until Feb.
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected.  
  • Wittson Hall – level 4 – Lab 4004. Completion in late December, furniture in January.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Feb.
  • Wittson Hall – level 3 – Hospitalist project phase 2 part 1, furniture install in December, opening late December. Part 2 – Furniture in late January, move in Feb early.
  • Wittson Hall – level 3 elevator lobby construction –December 18 to Feb
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Dec 18 to Feb
  • Wittson Hall – Level 2 – Family RR and CM breakroom complete in late Nov. Will move computer to breakroom shortly after.
  • Wittson Hall – main center staircase closed for construction – Now until Feb
  • Heritage Center furniture install starts mid-February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – April 2021
  • Heritage Center Completion of exhibits and audio visual – April 2021
  • Heritage Center Grand Opening – Late May 2021
  • University Tower – Levels 3-6 – Some areas will be ready for furniture after Thanksgiving.
  • Exterior – South Courtyard – Completion date coincides with Heritage.
  • Exterior – Northwall Plaza – completion late May 2021
  • Exterior – installation of plantings – likely April/May 2021 depending on weather for North and South Courtyard.  

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been hot and cold with construction workers but still an issue. Workers are now being monitored over lunchtime for proper separation.
    • Quality – punchlist timeliness has been an issue   
    • Schedule – Many areas have work happening. Covid has been an issue more and more it seems as the year goes on.
    • Budget – no contingency left.

Wittson/Wigton Update October 30

Progress Update:

  • Level 8 – abatement complete, Construction starting.
  • L8 Rare book room HVAC. Submittals are reviewed. Equipment had 17 notes from the engineer to incorporate. Drawings are being finalized with stamps from SES as well. Due date on those is Oct 30.
  • L8 non-library space – Hausmann has submitted pricing to UNMC – work is approved. Contracts are being put into place to incorporate this new work.
  • L7, L6 Punchlist, Furniture, McGoogan staircase construction ongoing, punch list walk complete. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Mechanical and electrical rough-ins continue. Topping out Drywall.
  • Wittson Hall – Level 4 – Closed for construction on main east west hall. Abatement taking place. Working on 42nd street vestibule (exterior wall is removed). Relocations in progress for MEP on areas where floor is to be removed.
  • Lab 4004 Constructing new HVAC and Electrical, ceilings, lighting. Casework starts 1st week of Nov.
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Ceiling grid/lights work is in progress.
  • L3 working on ceilings/paint in Hospitalist PH2
  • L2 working on locker rooms, touchup and small items. Completion Oct 25. There will be some small items left to do. Soap dispensers will be hand pump style until new ones arrive. Locker trims on order, installation soon.
  • L2 Sterilizer. Installation of sterilizer in progress. Met with Primus/Spire regarding needs for electrical.
  • Dimensional Innovations – Proposal request for construction needs is complete
  • AVISPL – Proposal request has been issued. Next scheduled walk through will be on Nov 2.
  • University Tower L3-L6 – working on terra cotta façade and windows, mechanical, electrical, framing, demo. Some windows were mis-measured by contractors and are being re-ordered, still no ETA on those.    
  • University Tower – east façade restoration work continues. Users please keep windows closed. Signs are posted.
  • Heritage, working on glass, mechanical and electrical. Focusing on high ceiling work first. (Perforated drywall, lighting). Historic replica terra cotta pieces about 90% installed.

Schedule

  • Wittson Hall – level 8 south (library collections) –abatement Schedule tentatively furniture start Late January. Move in Mid/Late-Feb.
  • Wittson Hall – level 8 Neb Med space – July/Aug 21’ – pending multiple phases.  
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in Late January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) until Feb.
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected.  
  • Wittson Hall – level 4 – Lab 4004. Completion in late December.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Feb.
  • Wittson Hall – level 3 – Hospitalist project phase 2, furniture install in December, opening late December.
  • Wittson Hall – level 3 elevator lobby construction –December 18 to Feb
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Dec 18 to Feb
  • Wittson Hall – Level 2 – Completion of Locker rooms open for use on Oct 26. Punchlist completion by mid Nov.
  • Wittson Hall – main center staircase closed for construction – Now until Feb
  • Heritage Center furniture install starts mid-February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – late March 2021
  • Heritage Center Completion of exhibits and audio visual – April 2021
  • Heritage Center Grand Opening – Late May 2021
  • University Tower – Levels 3-6 – Some areas will be ready for furniture after Thanksgiving.
  • Exterior – South Courtyard – Work has started. Completion date coincides with Heritage.
  • Exterior – installation of plantings – likely May 2021 depending on weather for North and South Courtyard. Working on foundation pricing for art pieces.

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been hot and cold with construction workers but still an issue. Workers are now being monitored over lunchtime for proper separation.
    • Quality – punchlist timeliness has been an issue   
    • Schedule – Many areas have work happening. Covid has been an on and off issue for a couple months now with certain key workers (foremen, office help)
    • Budget – no contingency left.

Wittson/Wigton Update October 23

Progress Update:

  • Level 8 – abatement nearly complete, cleaning up and moving out. Delayed the construction about 40 days. Other work is happening on L8 area. Mechanical and electrical. 
  • L8 Rare book room HVAC. Submittals are reviewed. Equipment had 17 notes from the engineer to incorporate. Drawings are being finalized with stamps from SES as well. Due date on those is Oct 30.
  • L8 non-library space – Hausmann has submitted pricing to UNMC – work is approved. Contracts are being put into place to incorporate this new work.
  • L7, L6 Punchlist, Furniture, McGoogan staircase construction ongoing, punch list walk scheduled for next week. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Mechanical and electrical rough ins continue.
  • Wittson Hall – Level 4 – Closed for construction on main east west hall. Abatement taking place. Working on 42nd street vestibule (exterior wall is removed). Relocations are starting for MEP on areas where floor is to be removed.
  • Lab 4004 Constructing new HVAC and Electrical, ceilings, lighting. Casework starts 1st week of Nov.
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Ceiling grid/lights work is in progress.
  • L3 working on ceilings/paint in Hospitalist PH2
  • L2 working on locker rooms, touchup and small items. Completion Oct 25. There will be some small items left to do. Soap dispensers will be hand pump style until new ones arrive. Locker trims on order, installation soon.
  • L2 Sterilizer. Moves Oct 28.
  • Dimensional Innovations – Designing proposal request with HDR to incorporate into drawings.  Everything is very close. Pending cable/fiber pull spreadsheet from DI.
  • AVISPL – Proposal request has been issued. Next scheduled walk through will be on Oct 30.
  • University Tower L3-L6 – working on terra cotta façade and windows, mechanical, electrical, framing, demo. Some windows were mis-measured by contractors and are being re-ordered, still no ETA on those. Potentially relocating one user on L3 to 3130. Schedule on UT work is forthcoming.
  • University Tower – east façade restoration work started. Users please keep windows closed. Signs are posted.
  • Heritage, working on glass, mechanical and electrical. Focusing on high ceiling work first. (Perforated drywall, lighting). Historic replica terra cotta pieces about 90% installed.

Schedule

  • Wittson Hall – level 8 south (library collections) – TBD – this has been delayed for multiple weeks due to abatement work taking place in the space. Schedule on this to be cleaned up late next week once contractors can gain traction. Still removing debris from demo.
  • Wittson Hall – level 8 Neb Med space – TBD – pending multiple phases. Will update schedule once we are further down. Summer of 21 most likely.
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in Late January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) until Feb.
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected.  
  • Wittson Hall – level 4 – Lab 4004. Completion in late December.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Feb.
  • Wittson Hall – Level 3 – piping work above ceilings in 3010 area Oct 26-30
  • Wittson Hall – level 3 – Hospitalist project phase 2, furniture install in December, opening late December. Several L3 offices will be unavailable (3067, 3066) Oct 19-29.
  • Wittson Hall – level 3 elevator lobby construction –December 18 to Feb
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Dec 18 to Feb
  • Wittson Hall – Level 2 – Completion of Locker rooms open for use on Oct 26. Punchlist completion by early Nov.
  • Wittson Hall – main center staircase closed for construction – Now until Feb
  • Heritage Center furniture install starts mid-February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – late March 2021
  • Heritage Center Completion of exhibits and audio visual – April 2021
  • Heritage Center Grand Opening – Late May 2021
  • University Tower – Levels 3-6 – TBD. Currently having issues with windows that were mis-measured.
  • Exterior – South Courtyard – Work has started. Completion date coincides with Heritage.
  • Exterior – installation of plantings – likely May 2021 depending on weather for North and South Courtyard. Working on foundation pricing for art pieces.

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been hot and cold with construction workers but still an issue. Workers are now being monitored over lunchtime for proper separation.
    • Quality – punchlist timeliness has been an issue   
    • Schedule – Many areas have work happening. Covid has been an on and off issue for a couple months now with certain key workers (foremen, office help)
    • Budget – no contingency left.

Williams Science Hall October 16 Update

Progress Update:

  • Building Access update – 2nd floor South entrance is closed 2 new, temporary, 1st floor entrances available.
    • 3rd floor East entrance with card access is unchanged (card reader is working)
    • Public elevators are operational!!!
  • 3rd Floor access to Central Stairwell is closing 10/15 for 3 weeks (CRA was 10/6)
  • 4th floor access to Central Stairwell will close for 4-6 hour window to abate the flooring and then reopened. The 3 week closure is cancelled at this time.
  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – slight delay awaiting a final valve.  Water will continue to be supplied.
  • Air Handler 2 – shutdown of existing and tie-in to new unit – Tentatively scheduled for 11/9; this work is anticipated to last 5 days just like we did for AHU1 – CRA pending.

Phase 1:

3rd & 4th Floors

  • Punch list items near completion
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).

1st & 2nd Floors

  • Glass railing system atrium stairs is onsite – installation almost complete!
  • Flooring installation is finalizing – Atrium stair area and main entrance remains
  • Above Ceiling and Electrical inspections complete
  • Room/door signage installation started, completion pending
  • Punch list walk by RDG 10/13
  • SFM walk for temp C of O – 10/8 – fire systems tested and space was approved to allow the elevators to be turned on and provide emergency exits through finished space. The exits are designated with cones, rope, barricades, and signage.

Phase 2:

  • Electrical demo and temp lighting is ongoing – focusing on 2nd and 3rd floors
  • Casework and full demo underway
  • Abatement of “black glue” beneath the flooring that was demoed will start week of 10/12
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started on North & South facades
  • Landscaping at main entrance – concrete planters poured and site cleared for paver installation

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy) – SFM walked, C of O is pending
  • Phase 2 4th floor on hold temporarily
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions – change orders
    • Freight Elevator
    • TC area
    • Equipment room – emergency power

Decisions or Resources Needed: Extensive review of the budget and anticipated spend is underway with extended construction schedule.

Williams Science Hall October 9 Update

Progress Update:

  • Building Access update – 2nd floor South entrance is closed 2 new, temporary, 1st floor entrances available.
    • 3rd floor East entrance with card access is unchanged (card reader is working)
    • Public elevators are operational!!!
  • 3rd Floor access to Central Stairwell is closing 10/15 for 3 weeks (CRA was 10/6)
  • 4th floor access to Central Stairwell will close for 4-6 hour window to abate the flooring and then reopened. The 3 week closure is cancelled at this time.
  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – slight delay awaiting a final valve.  Water will continue to be supplied.
  • Air Handler 2 – shutdown of existing and tie-in to new unit – Tentatively scheduled for 11/9; this work is anticipated to last 5 days just like we did for AHU1 – more info to come.

Phase 1:

3rd & 4th Floors

  • Punch list items near completion
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).

1st & 2nd Floors

  • Glass railing system atrium stairs is onsite – installation is progressing
  • Flooring installation is finalizing
  • Above Ceiling and Electrical inspections complete
  • Room/door signage installation started, completion pending
  • Punch list walk by RDG 10/13
  • SFM walk for temp C of O – 10/8 – fire systems tested and space was approved to allow the elevators to be turned on and provide emergency exits through finished space. The exits are designated with cones, rope, barricades, and signage.

Phase 2:

  • Electrical demo and temp lighting is ongoing – focusing on 2nd and 3rd floors
  • Casework and full demo underway
  • Abatement of “black glue” beneath the flooring that was demoed will start week of 10/12
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started on North facade
  • Landscaping at main entrance – frames for concrete planters

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy) – SFM walked, C of O is pending
  • Phase 2 4th floor on hold temporarily
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed: None at this time.

Wittson/Wigton October 9 Updates

Progress Update:

  • L3 electrical work on Oct 12 – lighting will be off (except emergency egress lighting) from 6pm to midnight.
  • Level 8 – demo still in progress. Working on abatement. Starting mechanical installation
  • L8 Rare book room HVAC. Submittals are reviewed. Sent to Hausmann for ordering equipment.
  • L8 non-library space – Hausmann has submitted pricing to UNMC
  • Punchlist, Furniture, Move-in on Level 7 and 6 – still HCI working on punchlist items, a few extras are being planned/quoted, McGoogan staircase construction ongoing. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Mechanical and electrical rough ins have started.
  • Wittson Hall – Level 4 –Working on closing main east west hall. Working on 42nd street vestibule (exterior wall is removed). Removing flooring will take place soon. Date will be given so users know when the noisy work will start up again.
  • Lab 4004 Constructing new HVAC and Electrical services.  
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Ceiling soffit framing work is in progress
  • L3 working on ceilings/paint in Hospitalist PH2
  • L3 working on office 3077 wall/door. Fire sprinkler lines in southwest corner of L3 is complete
  • L2 working on locker rooms, ceilings and inspections. Lockers on L2 will be moved into the L2 locker rooms on Oct 14-16.  Completion Oct 19.
  • L2 Sterilizer. Meeting Tuesday to walk the path that the unit can take from ESH through PYH and into WHM on level 2.
  • Dimensional Innovations –Reviewing plans with HDR to incorporate into drawings. HDR asking for additional funds to incorporate plans. UNMC believes this should be in scope
  • AVISPL – HDR is very close to issuing the proposal request with details on the infrastructure adds.
  • University Tower L3-L6 – Vertical riser duct complete. Damper motors installed. Completing shaftwall work can start.
  • University Tower – east façade restoration work starts Monday with workers on a swinging stage outside the building. Users please keep windows closed. An email notice will be sent.
  • Heritage, working on glass, mechanical and electrical. Focusing on high ceiling work first. (Perforated drywall). Historic replica terra cotta pieces about 70% installed. Restoration work on UT columns continues.

Schedule

  • Wittson Hall – level 8 south (library collections) – TBD – this has been delayed for multiple weeks due to abatement work taking place in the space.
  • Wittson Hall – level 8 Neb Med space – TBD based on design change approvals.
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) Oct 12 to Feb
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected.  
  • Wittson Hall – level 4 – Lab 4004. Completion in late December.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Feb 1.
  • Wittson Hall – level 3 – Hospitalist project phase 2, furniture install in early December, opening late December.
  • Wittson Hall – level 3 elevator lobby construction – Mid December to Feb 1.
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Mid Dec to Feb 1
  • Wittson Hall – Level 2 – Moving L2 lockers to new locker rooms Oct 14-16. Completion of Locker rooms open for use on Oct 19. Punchlist completion by November 6.
  • Wittson Hall – main center staircase closed for construction – Late-October to Feb 15, 2021
  • Heritage Center furniture install starts mid-February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – late March 2021
  • Heritage Center Completion of exhibits and audio visual – early April 2021
  • University Tower – Levels 3-6 – furniture starts November 15, occupancy in December.
  • Exterior – South Courtyard – Work has started. Completion date coincides with Heritage.
  • Exterior – installation of plantings – likely spring of 2021 depending on weather for North and South Courtyard. Working on foundation designs for art pieces with HDR. Design for  phase 1 foundation piece is in final stages

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been better with construction workers but still an issue
    • Quality – punchlist timeliness has been an issue,  
    • Schedule –   
    • Budget – no contingency left.

Wittson / Wigton Heritage Center October 2 Update

Progress Update:

  • Power outage – notice previously sent regarding power/HVAC outage for Oct 3.
  • Steam outage – this should not have much impact on comfort. Planned for Oct 7.
  • Level 8 – demo still in progress. Working on abatement. Starting mechanical installation
  • L8 Rare book room HVAC. Working on contract details pertaining to insurance values. SES Engineering reviewed submittals for HVAC equipment. Sent to Hausmann for comment.
  • L8 non-library space – Changes to plans are being finalized. Hausmann is working on pricing for this change.
  • Punchlist, Furniture, Move-in on Level 7 and 6 – still HCI working on punchlist items, a few extras are being planned/quoted, McGoogan staircase construction ongoing. Several small items left to do/improve.
  • Level 5 – Framing new offices currently. Fin tube heaters on west side removed. MEP rough in have started.
  • Wittson Hall – Level 4 – Noisy work is complete. Working on closing main east west hall. Working on 42nd street vestibule (exterior wall is removed). Removing flooring will take place soon. Date will be given so users know when the noisy work will start up again.
  • Lab 4004 Demo complete. Constructing new HVAC and Electrical services.  
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair.   Ceiling soffit framing work is in progress
  • L3 working on ceilings/paint in Hospitalist PH2
  • L3 working on office 3077 wall/door. Fire sprinkler lines in southwest corner of L3 is complete
  • L2 working on locker rooms, ceilings and inspections. Lockers on L2 will be moved into the L2 locker rooms on Oct 14-16.  Completion Oct 19.
  • L2 Sterilizer. Planning is taking place to remove wall 2099A in PYH so that the sterilizer can move through. Door, frame, hardware, card access, portion of drywall and wall itself will be removed in order to make this happen. A schedule on this will be sent out Monday.
  • All floors – work for planning and drawings is taking place for exhibit installations with Dimensional Innovations.
  • University tower L3-L6 – working on progress on vertical HVAC risers which serve Heritage atrium. Finishing soon, then shaftwall work can start.
  • Heritage, working on glass, mechanical and electrical. Focusing on high ceiling work first. Historic replica terra cotta pieces have arrived, that work continues. Restoration work on UT columns continues. Discussions/planning/work has started on locations that will accommodate AVISPL displays.

Schedule

  • Wittson Hall – level 8 south (library collections) furniture starts Dec 1, 2020, Move in Late Dec 2020.
  • Wittson Hall – level 8 Neb Med space – TBD based on design
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in January 2021, move in February 2021.
  • Wittson Hall – level 5 – work in elevator lobby, elevators will be unavailable Nov 30 to end of December.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) Sept 30 to Feb  
  • Wittson Hall – level 4 – Coffee Cart – completion will depend on vendor selected. From what I hear Scooters chain is interested in the project.
  • Wittson Hall – level 4 – Lab 4004. Completion in December.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and Bennett (closed for construction) – Mid-December to early January – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction Dec to Feb 1.
  • Wittson Hall – level 3 – Hospitalist project phase 2, furniture install in early December, opening late December.
  • Wittson Hall – level 3 elevator lobby construction – Mid December to Feb 1.
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. (rooms will be available – Mid Dec to Feb 1
  • Wittson Hall – Level 2 – Moving L2 lockers to new locker rooms Oct 14-16. Completion of Locker rooms open for use on Oct 19. Punchlist completion by November 6.
  • Wittson Hall – main center staircase closed for construction – Late-September to Feb 1, 2021
  • Heritage Center furniture install starts mid February 2021
  • Heritage Center first use of space – early March 2021
  • Heritage Center punchlist completion – late March 2021
  • Heritage Center Completion of exhibits and audio visual – early April 2021
  • University Tower – Levels 3-6 – furniture starts November 1, occupancy in December.
  • Exterior – South Courtyard – Completion date coincides with Heritage completion.
  • Exterior – installation of plantings – likely spring of 2021 depending on weather for North and South Courtyard. Working on foundation designs for art pieces with HDR. Design for  phase 1 foundation piece is in final stages

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – mask wearing has been better with construction workers but still an issue
    • Quality – punchlist timeliness has been an issue,  
    • Schedule –   
    • Budget – no contingency left.

Williams Science Hall October 2 Update

Progress Update:

  • RO System Replacement almost complete
    • Estimated duration is 4 weeks – 9/8 to 10/6
  • Air Handler 2 – 1 day shutdown for tie-in – this will be October/early November timeframe
  • Building Access update – 2nd floor South entrance is closing, 2 new, temporary, 1st floor entrances available. (See attached plans).
    • 3rd floor East entrance with card access is unchanged

Phase 1:

3rd & 4th Floors

  • Punch list items underway – due 10/5
  • Fume hood modifications are underway by Waldinger – 1 hour per fume hood (max) and light noise expected (drill).
    • They are installing a “pan” that will allow the existing hood to operate in the new variable air flow system and, ultimately, complies with building code

1st & 2nd Floors

  • Electrical and plumbing work is finalizing
  • IT cabling is complete and terminated in new IT closets
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
  • Ceiling grid installed
  • Light fixtures installed
  • Flooring installation is finalizing
  • Above Ceiling and Electrical inspections to be complete
  • Room/door signage installation started, complete week of 10/5
  • Punch list walk by RDG 10/5
  • SFM walk for temp C of O – 10/8

Phase 2:

  • Waldinger removed both Bio Safety Cabinets from TC room; will remove fume hoods from 3005 and 4023
  • Electrical demo and temp lighting is ongoing
  • Corridor work and impact under review – CRA will be week of 10/5
  • Casework and full demo underway
  • TC room design to include 2 separate rooms with one vestibule/ante room

Exterior:

  • Column Framing has started
  • Landscaping at main entrance – frames for concrete planters
  • SW soffit is repaired and finished   

Schedule

  • 10/8 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • 11/6 – tentative Phase 2 4th floor North half to start
  • Contractor Substantial Completion: 03/15/21
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
    • Central stair and corridor work coordination and closure
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
    • Walk occurred with Dr. Lyubchenko week this week
    • Meeting scheduled with Dr. Murry for 10/5
  • Budget: “less than” mindset
    • Abatement – black glue under VCT flooring
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed: None at this time.

Tissue culture casework ready for demo. The green is original to 1975.
Atrium feature wall – painted, before the new paneling was installed.

Williams Science Hall Update

Progress Update: Not a lot of change from last week as we wrap up Phase 1 levels 3 and 4 for partial occupancy

  • Air Handler 2 – delivery schedule for September 1-2
    • Crane onsite on the East side of the building – 2 days
    • 1 day shutdown for tie-in – this will be October timeframe
  • Flooring installation complete on 3rd and 4th floors
  • Ceiling is installed on 3rd & 4th
  • Restroom tiling finishing on 1st floor; final fixture installation
  • New RO piping installed in Phase 1
    • RO System shutdown planned for Tuesday, 9/8 – water will be supplied during this time
    • Estimated duration is 4 weeks
  • Electrical and plumbing work is finalizing on 3rd and 4th; ongoing on 1st and 2nd  
  • HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
  • IT closets are all set – new switch installation starting today!
  • IT cabling is complete – awaiting termination
  • Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
  • New door installation in progress on 2nd and 1st
  • Card reader rough-ins – need IT
  • Elevators and Elevator lobbies:
    • Interior finishes ordered
    • Floor leveler installation 8/31
  • Exterior:
  • EIFS work started on North and West facades 
    • The underside of the soffit on the Southwest corner was demoed
    • New glass installed with fritted pattern – almost complete

Schedule

  • 9/3 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
  • 9/8 – relocations of Phase 2 occupants to start
  • 9/10 – Phase 2, 4th floor, South ½ work to begin
  • 9/14 – Phase 2, 3rd floor work to begin
  • 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
  • Contractor Substantial Completion: 03/15/20
  • First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
    • 1st series of moves are Phase 2 occupants over to Phase 1 space

Budget Status:

  • Approved Budget = $12,673,300
  • Planned Spend = $12,587,799

Key Risks or Issues:

  • Occupied Building and impact during building system shut-downs and construction activities in Phases
  • New IT closets activated / jack activation for Phase 1 occupants and transition in Phase 2
  • Occupied labs (Murry/Lyubchenko) and scope of work coordination
  • Budget: “less than” mindset
    • Abatement
    • Phase 2 conditions
    • Freight Elevator

Decisions or Resources Needed:

  • None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.