Progress Update:

  • Exterior – Material delivered for screen wall at north side of Heritage.
  • L5 –Cabinets for 5025 are being built
  • L6/7 – Budget/approval in process for wall guard for library study rooms
  • L8 North & West – working on card access doors

Schedule:

  • Re-scheduled fire alarm testing for Nov 23 at 8:30am. All alarms will sound on all floors for approx. 30 minutes
  • L6 staircase – Laminate work starting 12-16-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M