Wittson/Wigton November 12 update

Progress Update:

  • Exterior – working on downspout on south side of Heritage. Also working on screen wall at north side of Heritage.
  • L5 –Cabinets for 5025 are being built
  • L6/7 – Working planning for wall guard cost for library area
  • L8 North & West – working on card access doors

Schedule:

  • Window cleaning in Heritage levels 3-6 – Nov 17 and 18
  • Re-scheduled fire alarm testing for Nov 23 at 8:30am. All alarms will sound on all floors for approx. 30 minutes
  • L6 staircase – Laminate work starting 12-16-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M