Central Campus Construction

Wittson/Wigton November 5 Update

Progress Update:

  • Fire Marshal will be walking through and inspecting the building Nov 9 at 9-10am. Fire alarm system may sound. Please Disregard this testing.
  • Exterior – working on downspout on south side of Heritage. Also working on screen wall at north side of Heritage.
  • L5 –Cabinets for 5025 are in process (materials on order)
  • L6/7 – Working on re-pricing for wallguard cost for library area
  • L8 North&West – working on card access doors

Schedule:

  • L6 staircase – Laminate work starting 12-16-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M