Wittson/Wigton October 22 Update

Progress Update:

  • Exterior – work outside of Heritage for re-sloping brick pavers scheduled for the 28th-Nov 1st  of Oct
  • L5 –Cabinets for 5025 are in process (materials on order)
  • L6/7 – Working on pricing for acoustic panels cost for Library area
  • L8 North&West – punch list

Schedule:

  • L6 staircase – Laminate work starting 12-16-21
  • North Plaza – Screen wall work starts October 28
  • Service elevator will be offline on Oct 29 for renovation

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M