Central Campus Construction

Wittson/Wigton October 1 Update

Progress Update:

  • Fire alarm testing Thursday Oct 7 (7-8am)
  • Service Elevator – offline for new improvements – October 7-10th
  • L8 North&West – final furniture installations, cleanup, data jack coordination
  • L5 –carpeting 5030  and hallway outside on Monday the 4th

Schedule:

  • L8 – NM Pulmonary space – Move-in starting October 11
  • L6 staircase – Laminate work starting 12-16-21
  • L3 – replacement furniture for Rheum – Oct 5 installation
  • North Plaza – Screen wall work starts mid October

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Leave a Reply