Progress Update:

  • L8 North&West – installation of furniture starting – finishing of punchlist work
  • L4 – wall guard finishing outside labs 4033, 4037, 4038.
  • North plaza – minor grading work continues

Schedule:

  • L8 – NM Pulmonary space – Move-in early October
  • L6 staircase – Laminate work starting 12-16-21
  • L5 – moving furniture, installing carpet on September 3-5
  • L4 –hallway work to be complete by Sept 7
  • L4 – carpet work on north hallway on 8-28-21
  • North Plaza – Screen wall work starts 9-3-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M