Central Campus Construction

Wittson/Wigton August 27 Update

Progress Update:

  • L8 North&West – move out materials, touch ups, doors&hardware
  • L4 – wall guard installation taking place outside labs 4033, 4037, 4038.
  • L3 – Punch list items, wall guard installation – to be complete Aug 30
  • Bennett Ramp – installing traffic device and clearance bar. Will be complete by Aug 30
  • North plaza – grading work for rock area continues

Schedule:

  • L8 – NM Pulmonary space – September 1 furniture start. Move-in late Sept.
  • L6 staircase – Laminate work starting 12-16-21
  • L5 – moving furniture, installing carpet on Sept 3-5
  • L4 –hallway work to be complete by Sept 7
  • L4 – carpet work on north hallway on 8-28-21
  • North Plaza – Screen wall work starts 9-3-21

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M