Central Campus Construction

Wittons/Wigton August 13 Update

Progress Update:

  • L8 North&West – Inspections, Ceiling pads, Electrical, Lighting, Paint, Carpet, Doors&HW
  • L6 – Work in Stair A (drywall) – painting
  • L5 Continuing work on door replacements at stairwells
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4 – working on door replacement at Sorrell skywalk – skywalk will remain open Monday through Friday – Skywalk will be closed Saturdays Aug 14
  • L4/L3 – Punch list items, wall guard installation – to be complete Aug 30
  • Exterior – Emile Ramp – lighting along wall will continue through next week.
  • Bennett Ramp – installing traffic device and clearance bar. Will be complete by Aug 30

Schedule:

  • L8 – NM Pulmonary space – September 1 furniture start. Move-in late Sept.
  • L6 staircase – Laminate work starting 12-16-2021
  • L5 – moving furniture, installing carpet on Aug 27 and Sept 3
  • L5 – coordinating dates for carpet replacement with L5 offices
  • L5 – moving furniture pieces etc. 5030 to 5027 and 3044 on 8-10-21.
  • L4 – door and hallway work to be complete by Aug 30
  • Northwall – minor work in river rock area on Aug 20. Inlet work starting Aug 16.

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M