Central Campus Construction

Wittson/Wigton July 30 Update

  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades 7-26 to 8-3. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Ceiling pads, Electrical, Lighting, Paint, Carpet, Doors&HW
  • L6 – Work in Stair A (drywall) – from existing sprinkler leak
  • L5 Continuing work on door replacements at stairwells
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4/L3 – Punch list items, wall guard installation
  • Exterior – Emile Ramp – lighting along wall starting 7-26 – will continue through next week.

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – Laminate work starting 12-16-2021
  • L5 – coordinating dates for carpet replacement with L5 offices

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M