Central Campus Construction

Wittson/Wigton July 23 Update

  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades the week of 7-26. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting, Paint, Carpet
  • L6 – Work in Stair A to repair existing fire sprinkler system drain lines.
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained
  • L4/L3 – Punch list items, wall guard installation
  • L3 Hospitalist PH 2 part 3 – complete
  • Level 3 – south hallway work outside CAST – complete
  • Exterior – Emile Ramp – lighting along wall starting 7-26

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – Laminate is here. Coordinating a start date. 5-8 week install process.
  • L5 – Starting work on Door replacements at N and S stairways on L5 on Saturday July 24

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M