Central Campus Construction

Wittson/Wigton July 16 Update

  • Bennett Hall exterior drive will be out of service for construction Sunday July 18 from 6am to 4pm for work related to traffic control system.
  • Inside Wittson/Bennett on Level 4 – Skywalk will be closed for construction upgrades the week of 7-19. Sorrell skywalk will remain accessible.

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting, Paint, Carpet
  • L8 – Rare book room (north) – Complete
  • L6 – Work in Stair A to repair existing fire sprinkler system drain lines.
  • L4/L3 – Punch list items
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 punchlist
  • Level 3 – south hallway work outside CAST – working on touch ups
  • Exterior – Emile Ramp – lighting along wall starting next week.

Schedule:

  • Wittson Hall – level 8 NM Pulmonary space – September move in
  • L6 staircase – TBD based on laminate delivery.  
  • L5 – Starting work on Door replacements at N and S stairways on L5 on Saturday July 24
  • L4 – Dunkin – Opening date for selling coffee is around July 22.
  • L4 – construction work taking place next week outside labs 4033, 4037, 4038. Access to these labs will be maintained

Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M