Wittson/Wigton July 2 Update

Progress Update:

  • L8 North&West – Inspections, Drywall, Mechanical, Electrical, Lighting
  • L8 – Rare book room (north) – Working on insulation, completion of the North RBR mech room. Still some programming and controls work to do on these units.
  • L6 – starting work soon on Stair A to repair old sprinkler system drain.
  • L4/L3 – Punch list items
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • Level 3 – Started south hallway work outside CAST    
  • Heritage – Working on Canopy
  • Exterior – Northwall Plaza – lighting, benches,  
  • Exterior – Emile Ramp – lighting along wall.

Schedule:

  • L8 Library – RBR hvac finishing soon
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Dunkin – Opening date for selling coffee is around July 7.
  • L4 – Work around new Dunkin space is 99% complete. Date of open sales is between July 7-12.
  • L3 – hallway work outside CAST – completion approx. July 14
  • Bennett Ramp – traffic control device work starts tomorrow (Saturday) – for a few hours the ramp will be obstructed while loop sensors are installed.
  • Heritage Center Completion of audio visual – Substantially complete
  • Heritage Center Grand Opening – June 29 
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  