Central Campus Construction

Wittson/Wigton June 25 update

Progress Update:

  • L8 North&West – Inspections on top of wall. Drywall top out 1 side.
  • L8 – Rare book room (north) – Working on installation of new hvac unit.
  • L4 – Work around new Dunkin space is 99% complete. Date of open sales is TBD.
  • L4/L3 – Working on 42nd street vestibule touch ups
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • L2 – cleanup/punchlist.
  • Heritage – Working on Canopy,  
  • Exterior – Northwall Plaza – lighting, benches,  
  • Exterior – Emile Ramp – lighting along wall.

Schedule:

  • L8 Library – RBR hvac finishing soon
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Coffee Cart – Tentative ETA on completion – June 30.  
  • Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens (Starting June 30th – 2 week duration).  
  • Heritage Center Completion of audio visual – Substantially complete
  • Heritage Center Grand Opening – June 29 
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  