  • 42nd street will be closed on June 14 – 6pm to 2am.
    • A crane will be in the street to lift the Convergence sculpture up over the Poynter skywalk into the Northwall Plaza.
    • 42nd street will will be back open on June 15 at 2am.

Progress Update:

  • L8 North&West – Inspections on top of wall. Drywall top out 1 side.
  • L8 – Rare book room – Working on removal of south temp hvac unit and converting over to permanent unit.
  • L4 – Work around new Dunkin space, temp wall removal starts June 11. Hallway work south side. Touch ups in hallway intersection.
  • L4/L3 – Working on 42nd street vestibule, Door automatics in process. Electronics delay in auto operators/card readers.
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • AVISPL – Working on programming finishing touches.
  • Heritage – Working on Canopy, punchlist
  • Exterior –  complete.
  • Exterior – Northwall Plaza – lighting, benches, pavers, landscaping, irrigation system
  • Exterior – Emile Ramp – light bases, stucco, paint, wall lighting soon

Schedule:

  • L8 Library – touchups in common space rooms. Moving over to temp unit cooling next week.
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L6 staircase – TBD based on laminate delivery.  
  • L4 – Coffee Cart – Tentative ETA on completion – June 23-30. Temp wall around coffee bar to be removed June 11
  • Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens.  CAST will have time to coordinate schedules before hallway closes.
  • Heritage Center Completion of audio visual – Substantially complete
  • Exterior – Northwall Plaza – dedication June 16
  • Heritage Center Grand Opening – June 29 (private event June 10)
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  

Leave a Reply