Central Campus Construction

Wittson/Wigton May 28 update

Progress Update:

  • Construction closure of the Wittson-Bennett Skywalk starting May 21 and finishing June 4. The skywalk to Sorrell will be unaffected.
  • L8 North&West – Installation of HVAC duct in progress, framing, electrical
  • L8 – Rare book room – Working on removal of south temp hvac unit and converting over to permanent unit.
  • L5 – installation of new glass door & wall in progress. Dimensional Innovations (exhibit) work touch ups
  • Wittson Hall – level 5 – power and data for 5025.
  • L4 – Dimensional Innovations (exhibit) work nearly complete. Exhibits are shrouded. Work around new Dunkin space. Hallway work south side.
  • Lab 4004. HCI working on card access.
  • L4/L3 – Working on 42nd street vestibule, Door automatics in process. Medallion is installed.
  • Wittson Hall – Level 2 – finishing touches on CM breakroom.
  • AVISPL – Working on programming finishing touches.
  • Heritage – Working on Canopy, punchlist
  • Exterior – South Courtyard – working on sprinklers, lights, landscaping etc.
  • Exterior – Northwall Plaza – light pole bases, concrete stripes. Pavers and benches next week.   
  • Exterior – Emile Ramp – light bases start installing next week

Schedule:

  • L8 Library – Center section construction to be complete by June 1. South RBR unit to be operational by June 1.
  • Wittson Hall – level 8 NM Pulmonary space – Late Aug 21’  
  • L7 – Wallpaper work starts June 1.
  • L6 staircase – TBD
  • L4 – Coffee Cart –Tentative ETA on completion –June 23-30. Temp wall around coffee bar to be removed approx. June 14
  • L3 Hospitalist PH 2 part 3 – Office work in 3044 progressing
  • Wittson Hall – Level 3 – South Hallway outside CAST – new ceiling, lights to start after 42nd St. vestibule opens. Hallway paint will start happening June 1.
  • Heritage Center Completion of audio visual – Substantially complete, minor programming edits ongoing. Done by June 9
  • Heritage Center Grand Opening – June 29 (private event June 10)
  • Exterior – South Courtyard – June 1 Sculpture installation, Dedication June 10
  • Exterior – Northwall Plaza – dedication June 16
  • Budget Status: Approved Budget = 31.4M Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety – No issues
    • Quality – punchlist timeliness has been an issue   
    • Schedule – see above
    • Budget –  