Central Campus Construction

Wittson/Wigton January 22 Update

Progress Update:

  • L8 – working on framing and drywall, Mechanical HVAC installations.
  • L8 – Rare book room HVAC. Budget addenda has been approved today. Equipment engineering documents are under review.
  • L7, L6 – Punchlist, Furniture, McGoogan staircase work ongoing, few small items left to do.
  • L5 – Drywall tape and finish. Painting inside Wittson. Framing and installing drywall inside Heritage including Multitaction Wall, Restroom work including partitions and countertops. Ceiling framing, Lighting
  • L4 – Closed for construction on main east west hall. Working on 42nd street vestibule (exterior wall is removed). Relocations in progress for MEP on areas where floor is to be removed. Structural work at vestibule continues. Restroom work including partitions and countertops.  Working on west side construction of new connection point to Heritage MEP.
  • Lab 4004. Finishing last steps, data, AV, key cores
  • L3 currently a construction zone in the center of the east-west hallway. Stair access is closed to L3 at center stair. Flooring in progress
  • L3 working on punchlist in Hospitalist PH2 part 1. Phase 2 part 2 Electrical/Mechanical/ceiling installation.
  • L2 laminate on order to do trim between lockers.
  • L2 Sterilizer. Installation of sterilizer in progress. Sheetmetal enclosure complete on 1 side. Installation of condensate cooler/trap will start Monday.
  • Dimensional Innovations – Working through exact needs and coordination with construction – ongoing.
  • AVISPL – on site this week pre-wiring for the L4 and L5 screens.
  • University Tower L3– working on mechanical/electrical. Windows arrival ETA Jan 26. Wallpaper removal and tape/finish/paint in progress.
  • University Tower L3 hallway – Will be renovated by Core Construction, coordination in progress.
  • University Tower Exterior Restoration –South side will start once south sitework is complete.
  • Heritage – Lifts were removed this week. Flooring starts.
  • Exterior – South Courtyard – working on site paving.  
  • Exterior – Northwall Plaza – working on concrete bases for future hardscape,

Schedule

  • Wittson Hall – level 8 south (library collections) – furniture moves late February/early March, go live in March.
  • Wittson Hall – level 8 NM Pulmonary space – Aug 21’ – pending multiple phases.  
  • Wittson Hall – level 5 offices/catering/reception – Furniture starts in Late Feb, move in March 2021.
  • Wittson Hall – level 4 – construction in east-west corridor including elevator lobby (elevators will be offline level 4) until March.
  • Wittson Hall – level 4 – Coffee Cart – vendor “Dunkin Donuts” has been selected. Current completion date of Dunkin work is June 7 but discussions are going to be had to accelerate this date.
  • Wittson Hall – level 4 – Lab 4004. Completion in Feb.
  • Wittson Hall – Level 4 – Construction in skywalk between Wittson and – date will coincide with closure of L4 restrooms once new RR are able to be used.(Late Feb) – Sorrell skywalk will not be out of service at any time.
  • Wittson Hall – level 3 – 42nd street entrance/vestibule construction – coincide with opening of Heritage Center. Connection between hallway and vestibule will be under construction to April.
  • Wittson Hall – level 3 – Hospitalist project phase 2 part 1, installation of technology/data port activation progressing. Part 2 – Furniture in March, move in late March.
  • Wittson Hall – level 3 elevator lobby construction –December to Feb   
  • Wittson Hall – Level 3 corridor tie in with vestibule – North/South Hallway closed in middle section to tie in the 42nd street vestibule to east west hallway. – Dec to Feb
  • Wittson Hall – Level 2 – Family RR and CM breakroom complete in Jan. Will move computer to breakroom shortly after.
  • Wittson Hall – main center staircase closed for construction – Now until Mid-Feb
  • Heritage Center furniture install starts Late Feb/March
  • Heritage Center first use of space – late March
  • Heritage Center punchlist completion – April
  • Heritage Center Completion of exhibits and audio visual – April – Screen installation start March 1, Dimensional innovations start Feb 11.
  • Heritage Center Grand Opening – Late May
  • Exterior – South Courtyard – Completion date coincides with Heritage.
  • Exterior – Northwall Plaza – completion late May
  • Exterior – installation of plantings – likely April/May depending on weather for North and South Courtyard.  

Budget Status:

  • Approved Budget = 31.4M
  • Planned Spend = 31.4M

Key Risks or Issues:

  • Insert any project risks or issues being tracked, and any updates or action on issues since last update
    • Safety –
    • Quality – punchlist timeliness has been an issue   
    • Schedule – Covid has been an issue more and more it seems as the year goes on(material deliveries mostly impacted, manpower becoming more scarce)
    • Budget – no contingency left.