Progress Update:
- RO System shutdown planned for Tuesday, 9/8 – water will be supplied during this time
- 8 @ 5 gallon jugs were delivered; LCMS in route
- Estimated duration is 4 weeks
- Air Handler 2 – 1 day shutdown for tie-in – this will be October timeframe
3rd & 4th Floors
- SFM scheduled for 9/14 @ 9am for Certificate of Occupancy walk (vacation all next week) – a preliminary walk occurred 8/24
- 3rd and 4th floors are opening on a Conditional Temporary Certificate of Occupancy which allows us to move into the space prior to SFM walk
- Punch list items underway
- Phase 2 occupants moved 9/8-9/11 – almost complete
- 4th floor copier moved from 4010 to 4.0.002
- Break room on 4th off elevator lobby room 4.0.030A – Please do not use the sink at this time!
- Conference room moved from 4010 to the new area to room 4.0.003
1st & 2nd Floors
- Electrical and plumbing work is finalizing
- IT cabling is complete and terminated in new IT closets
- Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation is progressing
- Concrete poured on 1st floor complete
- New door installation in progress on 2nd and 1st
- Ceiling grid installation – light fixtures to follow
Phase 2: 4th (South half) and 3rd floor temp walls start 9/9 and 9/14
Other:
- Any building issues, please contact Erin Peters prior to contacting Facilities.
- Please report any elevator functional issues to Erin and she will reach out to O’Keefe
Exterior:
- EIFS work ongoing – major progress this past week
- The underside of the soffit on the Southwest corner was demoed
- Landscaping to start at main entrance 9/8 – delayed due to rain
Schedule
- 9/8 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
- 9/8 – relocations of Phase 2 occupants to start
- 9/10 – Phase 2, 4th floor, South ½ work to begin
- 9/14 – Phase 2, 3rd floor work to begin
- 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
- Contractor Substantial Completion: 03/15/20
- First Use of Space: Varies by temp Certificate of Occupancy; Erin will keep everyone informed as we near each groups move date
- 1st series of moves are Phase 2 occupants over to Phase 1 space
Budget Status:
- Approved Budget = $12,673,300
- Planned Spend = $12,587,799
Key Risks or Issues:
- Occupied Building and impact during building system shut-downs and construction activities in Phases
- Occupied labs (Murry/Lyubchenko) and scope of work coordination
- Budget: “less than” mindset
- Abatement
- Phase 2 conditions
- Freight Elevator
Decisions or Resources Needed:
- None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.
Questions? Contact Erin Peters