Progress Update: Not a lot of change from last week as we wrap up Phase 1 levels 3 and 4 for partial occupancy
- Air Handler 2 – delivery schedule for September 1-2
- Crane onsite on the East side of the building – 2 days
- 1 day shutdown for tie-in – this will be October timeframe
- Flooring installation complete on 3rd and 4th floors
- Ceiling is installed on 3rd & 4th
- Restroom tiling finishing on 1st floor; final fixture installation
- New RO piping installed in Phase 1
- RO System shutdown planned for Tuesday, 9/8 – water will be supplied during this time
- Estimated duration is 4 weeks
- Electrical and plumbing work is finalizing on 3rd and 4th; ongoing on 1st and 2nd
- HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
- IT closets are all set – new switch installation starting today!
- IT cabling is complete – awaiting termination
- Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
- New door installation in progress on 2nd and 1st
- Card reader rough-ins – need IT
- Elevators and Elevator lobbies:
- Interior finishes ordered
- Floor leveler installation 8/31
- Exterior:
- EIFS work started on North and West facades
- The underside of the soffit on the Southwest corner was demoed
- New glass installed with fritted pattern – almost complete
Schedule
- 9/3 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
- 9/8 – relocations of Phase 2 occupants to start
- 9/10 – Phase 2, 4th floor, South ½ work to begin
- 9/14 – Phase 2, 3rd floor work to begin
- 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
- Contractor Substantial Completion: 03/15/20
- First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
- 1st series of moves are Phase 2 occupants over to Phase 1 space
Budget Status:
- Approved Budget = $12,673,300
- Planned Spend = $12,587,799
Key Risks or Issues:
- Occupied Building and impact during building system shut-downs and construction activities in Phases
- New IT closets activated / jack activation for Phase 1 occupants and transition in Phase 2
- Occupied labs (Murry/Lyubchenko) and scope of work coordination
- Budget: “less than” mindset
- Abatement
- Phase 2 conditions
- Freight Elevator
Decisions or Resources Needed:
- None at this time but will continue to coordinate with occupants and UNMC partners to keep progressing.