Progress Update: Not a lot of change from last week as we wrap up Phase 1 levels 3 and 4 for partial occupancy
- Domestic water shut-down – complete.
- Air Handler 2 – delivery tentatively – September 1-2
- Crane onsite on the East side of the building – 2 days
- 1 day shutdown for tie-in – this will be October timeframe
- Flooring installation 3rd floor in-progress
- Ceiling grid installation – complete
- Ceiling pads following final inspections
- Final Above Ceiling Inspections for 3rd and 4th
- Restroom tiling finishing on 1st floor; final fixture installation
- New RO System & piping
- Electrical and plumbing work is ongoing
- HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
- IT closets are being outfitted from top down – floor sealed, cabinets installed; UPSs, etc.
- IT cabling is complete – awaiting termination
- Glass walls on 3rd and 4th floors in atrium/elevator lobbies is complete
- Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
- New doors are installed on 3rd and 4th; working on 2nd and 1st
- Card reader rough-ins – need IT and power
- Elevators and Elevator lobbies:
- Interior finishes ordered
- Floor leveler installation prior to tile
- Exterior: No change this week.
- EIFS work to continue all next week on North and West facades
- The underside of the soffit on the Southwest corner was demoed
- New glass installed with fritted pattern – almost complete
- EIFS work to continue all next week on North and West facades
Schedule
- 8/28 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
- 9/2 – relocations of Phase 2 occupants to start
- 9/7 – Phase 2, 4th floor, South ½ work to begin
- 9/14 – Phase 2, 3rd floor work to begin
- 9/22 – Atrium and Phase 1 floors 1 and 2 (temp Cert. of Occupancy)
- Contractor Substantial Completion: 03/15/20
- First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
- 1st series of moves are Phase 2 occupants over to Phase 1 space
Budget Status:
- Approved Budget = $12,673,300
- Planned Spend = $12,587,799


Questions? Contact Erin Peters