Progress Update:
- Reminder: Domestic water shut-down – Saturday, 8/15, 8am to 12pm (sinks, toilets, drinking fountains, eyewash stations, and decon showers)
- Air Handler 2 – delivery and installation – pending new date (will be a Saturday)
- CRA pending – 1 day shutdown for tie-in (same as delivery day)
- Crane onsite on the East side of the building – 2 days
- Brick paver demo on 1st and 2nd floors – complete. (South entrance at later date)
- Flooring installation 3rd floor in-progress
- Ceiling grid installation – complete
- Ceiling pads following final inspections
- Final Above Ceiling Inspections for 3rd and 4th
- Restroom tiling finishing on 1st floor; fixture installation
- New RO System & piping
- Electrical and plumbing work is ongoing
- HVAC ductwork for AHU2 almost complete in preparation for the unit’s arrival
- IT closets are being outfitted from top down – floor sealed, cabinets on campus for switches; UPSs, etc.
- IT cabling is being installed
- Glass walls on 3rd and 4th floors in atrium/elevator lobbies is almost complete
- Glass railing system for 2nd floor catwalk and atrium stairs is onsite – installation has started
- New doors are onsite – installation following the flooring
- Card reader rough-ins
- Casework installed! (see pics)
- Elevators and Elevator lobbies:
- The power to both passenger elevators was restored for contractor use. This will help reduce traffic in the occupied area and increase efficiency in the construction area
- Interior finishes were approved and ordered
- Exterior: No change this week.
- EIFS work to resume 8/17 and continue all week on North and West facades
- The underside of the soffit on the Southwest corner to be replaced in its entirety
- New glass installed with fritted pattern – almost complete
- EIFS work to resume 8/17 and continue all week on North and West facades
Schedule
- 8/28 – 3rd & 4th floors complete on Phase 1 (temp Cert. of Occupancy)
- 9/1 – relocations of Phase 2 occupants to start
- 9/7 – Phase 2, 4th floor, South ½ work to begin
- 9/14 – Phase 2, 3rd floor work to begin
- 9/22 – Atrium and Phase 1 Insert the next upcoming project milestone(s) or major work – including GC and other services
- Contractor Substantial Completion: 03/15/20
- First Use of Space: Varies by temp Certificate of Occupancy; I will keep everyone informed as we near each groups move date
- 1st series of moves are Phase 2 occupants over to Phase 1 space
Budget Status:
- Approved Budget = $12,673,300
- Planned Spend = $12,587,799