Progress Update:
- Demolition on Level 8
- L8 Rare book room HVAC. Material submittals in process.
- Punchlist, Furniture, Move-in on Level 7 and 6
- Move out in progress on Level 5
- Lab 4004 working on Demo
- L4 hallway plastic taken down
- L4 working on west side construction of new connection point to heritage. MEP work.
- L3 working on plumbing above Rheum to service 4004
- L2 working on locker rooms, floor concrete, framing, drywall, plumbing
- L2 moving to L4, Setting up lockers for temp use (in session Aug 24)
- L2 – sterilizer moving over from Eppley Science around Aug 17
- pictures (see bottom)
Schedule
- North sidewalk closure – Aug 11
- Wittson East entrance closure – Aug 11
- Sterilizer moving from ESH – Aug 18
- Contractor Substantial Completion: Jan 1, 2021
- First Use of Space: March 1, 2021
Budget Status:
- Approved Budget = 30.66M
- Planned Spend = 30.66M
Decisions or Resources Needed:
- Need budget approval on Restoration and column work
- Need decisions made on L8 redesign