Central Campus Construction

Wittson/Heritage Center Project Update

Progress Update:

  • Demolition on Level 8
  • L8 Rare book room HVAC. Material submittals in process.
  • Punchlist, Furniture, Move-in on Level 7 and 6
  • Move out in progress on Level 5
  • Lab 4004 working on Demo
  • L4 hallway plastic taken down
  • L4 working on west side construction of new connection point to heritage. MEP work.
  • L3 working on plumbing above Rheum to service 4004
  • L2 working on locker rooms, floor concrete, framing, drywall, plumbing
  • L2 moving to L4, Setting up lockers for temp use (in session Aug 24)
  • L2 – sterilizer moving over from Eppley Science around Aug 17
  • pictures (see bottom)

Schedule

  • North sidewalk closure – Aug 11
  • Wittson East entrance closure – Aug 11
  • Sterilizer moving from ESH – Aug 18
  • Contractor Substantial Completion: Jan 1, 2021
  • First Use of Space: March 1, 2021

Budget Status:

  • Approved Budget = 30.66M
  • Planned Spend = 30.66M

Decisions or Resources Needed:

  • Need budget approval on Restoration and column work
  • Need decisions made on L8 redesign