Construction Activities:
- All floors:
- Air Handler One is operational
- Need IT cabling for Siemens Controls
- Priming and 1st coat – all floors
- Ceiling grid installation – all floors
- Restroom tiling finishing on 1st and 2nd floors
- Electrical and plumbing work is ongoing
- IT closets are being outfitted from top down; Switches to be installed once space is cooled
- Framing of North end feature wall has started
- Glass walls on 3rd and 4th floors in atrium/elevator lobbies has started
- Air Handler One is operational
- Elevators and Elevator lobbies:
- Both passenger elevators are temporarily shut down for construction activities in the lobby ceiling areas
- All elevator lobbies are behind the construction barrier
- North side of 2nd floor only
- South entrance TBD – likely at the end of the project for minimal impact
- Exterior:
- EIFS and other exterior work – North side demo and new caulking complete – still to paint
- New glass / framing is ongoing
- Glass installation continues on the atrium (replacement glass)
Safety:
- Only authorized personnel in the construction areas and only with PPE
- Please continue to report any issues (e.g. unexplained odors) as they arise
Schedule & Budget:
- Phase 1 and Atrium anticipated completion – An updated schedule was provided on July 1, by Meco-Henne. Facilities is evaluating.
- Phase 2 sub-phasing plan was submitted and I will schedule meetings with those affected by the work
- Budget items: no new issues; change order #3 final pricing received and Change order issued.
- Tracking under budget currently, the shift to Phase 2, relocations, and final move-in pricing to be considered
- Additional bike rack area presented on Southwest corner