Central Campus Construction

Wittson Hall/Heritage Center – construction updates

Heritage Center

  • Installation of concrete floors is now complete
  • Installation of rooftop air handling unit is now complete
  • Contractors are working on fireproofing steel and installation of roofing materials
  • In the next 2 weeks, glass will start to be installed on the exterior of the structure.

Wittson Hall

  • Level 7 – continues with installation and finishing of drywall
  • Level 6 – continues with painting and some finishes (light fixtures, tile, ceilings etc.) Glass installation on the new windows has started and will be finished this month.
  • Level 5 – contractors are working on creating of storage room off of the exterior south corridor
  • Level 4 – offices on the south west side are close to complete, final inspections and furniture pending. Furniture install April 6.
  • Level 3 – offices pending final inspections and completion of construction punchlist. Class Lab 3020 finishes are in progress

Upcoming milestones:

  • Connection of new Heritage structure through to Wittson Hall on Level 4.
  • Connection and moves of individuals in University Tower