WSH activities from this week and looking forward:
Phase 1 update:
Construction: Not much change – just everything is progressing.
- Noise levels are constant and vary day-to-day
- All floors:
- Metal stud framing, walls and ceiling soffits, and drywall is being hung
- Ductwork installation (supply/exhaust)
- Electrical and plumbing rough-ins – restroom plumbing lines are climbing from floor to floor.
- Fire sprinkler system design
- Construction Phase 1 perimeter – complete
- 2nd floor – new route maintains the CON/MSC thoroughfare.
- EVS closet relocation to 3rd floor
- Alexey office – relocation to 3017 – 12/12
- 3017 copier moving to 4010!! – 12/11
- Alumni Relations is moving to 2003A and B – 12/12
- 2nd floor – new route maintains the CON/MSC thoroughfare.
Safety:
- Only authorized personnel in the construction areas and only with PPE
- Please continue to report any issues (e.g. unexplained odors) as they arise
Exterior Work:
- North and West facades still need painted – pushed to Spring
Other issues/items:
- None at this time.
Schedule & Budget:
- Phase 1 anticipated completion June 2020
- Exhaust fan and AHUs – Spring 2020
- IT infrastructure on order
- Controls equipment on order
- Budget items:
- Firewatch
- Fume hood ductwork for teaching lab