  • Week of 12.9.19
    • Heritage
      • Steel Erection heavy equipment on site.
    • Wittson
      • Continuing work on Level 3 conference room, restroom  – Ceilings/Flooring
      • Level 3 Hospitalist project mechanical and electrical rough in installation
      • Class Lab 3020 Mechanical and Electrical Rough in.
      • Level 4 offices @ auditorium – abatement
      • Level 4 west side – installation of structural steel beams under roof
      • Level 6 drywall installation, Mechanical and Electrical.
      • Level 7 framing walls, Mechanical and Electrical.
    • Week of 12.16.19
      • Heritage
        • Steel Erection heavy equipment on site.
        • Starting work to close UT 4123 for construction of new hallway
      • Wittson
        • Continuing work on Level 3 conference room, restroom  – inspection next week
        • Level 3 Hospitalist electrical installation
        • Class Lab 3020 Mechanical, Electrical rough in installation.
        • Level 4 offices @ auditorium installing dampers, ductwork access panels
        • Level 4 west side – installation of steel beams under roof.
        • Level 6  drywall installation, Mechanical and Electrical.
        • Level 7  installation of blocking, framing south side
      • Week of 12.23.19
        • Heritage
          • Steel Erection heavy equipment on site.
          • Concrete installation on metal Decking
        • Wittson
          • Continuing work on Level 3 conference room, restroom  – Drywall
          • Level 3 Hospitalist drywall installation
          • Class Lab 3020 blocking installation
          • Level 4 offices @ auditorium installing dampers, ductwork access panels
          • Level 4 west side – installation of mechanical and electrical work
          • Level 6  starting to paint walls
          • Level 7  installation of blocking, framing south side
        • Week of 12.30.19
          • Heritage
            • Steel Erection heavy equipment on site.
            • Concrete installation on metal Decking
          • Wittson
            • Continuing work on Level 3 conference room, restroom  – Paint
            • Level 3 Hospitalist painting
            • Class Lab 3020 drywall installation
            • Level 4 offices @ auditorium – re inspection
            • Level 4 west side – installation of mechanical and electrical work.
            • Level 6  painting
            • Level 7   inspections, installation of drywall starts Jan 2.

Milestone Dates:

Dec 14th (weekend) and Dec 21 (weekend) removing concrete exterior walls along east face of building (42nd street will be shut down)

May 6, 2020: MLS Lab/Classroom 3020 needs to be up and running.

Jan 21, 2021: Go Live of entire project.