WSH activities from this week and looking forward:
Phase 1 update:
Construction:
- Noise levels are constant and vary day-to-day
- Metal stud framing and drywall underway on all floors
- 3rd floor modifications are complete on South side
- Ductwork installation underway on all floors
- Greenhouse demo complete, replacement roofing underway
- There were odors reported this week. These were identified as the roofing material
- Construction Phase 1 perimeter is in-process – no change this week.
- 2nd floor is partially complete – working on the plan for minimal south entrance closure and critical HVAC work
- EVS closet relocation to 3rd floor
- Alexey office – relocation to 3017,
- 1st floor in process
- 2nd floor is partially complete – working on the plan for minimal south entrance closure and critical HVAC work
Safety:
- Only authorized personnel in the construction areas and only with PPE
- Please continue to report any issues (e.g. unexplained odors) as they arise
- On that note – I will try to notify everyone in the building of potential odors ahead of time.
Exterior Work:
- North and West facades still need painted
Other issues/items: Not at this time.
Schedule & Budget: No change at this time.
- Phase 1 anticipated completion was April 2020, at this time, incorporating Phase Final items is expected to push out ~60 days (June 2020)
- Exhaust fan and AHUs – Spring 2020
- Budget items: no change
- Increased number of WAPs and impact – budget submitted
- Firewatch
- Minor floor plan changes reviewed, final, and moving forward
- Fume hood ductwork for teaching lab