Central Campus Construction

Wittson and Wigton updates and looking ahead

  • Week of 10.21.19
    • Heritage
      • Foundation work and Pilings– heavy equipment on site.
    • Wittson
      • Continuing work on Level 3 conference room, restroom – Drywall
      • Level 3 Hospitalist project wall framing on Level 3 South Side.
      • Class Lab 3020 demolition.
      • Level 4 offices @ auditorium – Drywall
      • Level 4 temp walls starting for Labs on west side.
      • Working on Level 6 mechanical and electrical rough in.
      • Working on Level 7 demolition.
      • Planning work for removing exterior wall precast concrete panel on Levels 6 through Level 8.
    • Week of 10.28.19
      • Heritage
        • Foundation work, grade beam concrete – heavy equipment on site.
      • Wittson
        • Continuing work on Level 3 conference room, restroom – Drywall
        • Level 3 Hospitalist project wall framing on Level 3 South Side.
        • Class Lab 3020 demolition.
        • Level 4 offices @ auditorium – Drywall
        • Level 4 temp walls starting for Labs on west side.
        • Working on Level 6 mechanical and electrical rough in.
        • Working on Level 7 framing walls.
        • Planning work for removing exterior wall precast concrete panel on Levels 6 through Level 8.
      • Week of 11.4.19
        • Heritage
          • Foundation work, grade beam concrete – heavy equipment on site.
        • Wittson
          • Continuing work on Level 3 conference room, restroom – Paint
          • Level 3 Hospitalist project wall framing on Level 3 South Side.
          • Class Lab 3020 Mechanical and Electrical Rough in.
          • Level 4 offices @ auditorium – Paint
          • Level 4 demolition for Labs on west side.
          • Working on Level 6 Drywall.
          • Working on Level 7 framing walls.
          • Tentatively removing exterior wall precast concrete panel on Levels 6 through Level 8.
        • Week of 11.11.19
          • Heritage
            • Starting Steel Erectionheavy equipment on site.
          • Wittson
            • Continuing work on Level 3 conference room, restroom – Ceilings/Flooring
            • Level 3 Hospitalist project wall drywall on Level 3 South Side.
            • Class Lab 3020 Mechanical and Electrical Rough in.
            • Level 4 offices @ auditorium – Ceilings/Flooring
            • Level 4 installation of Mechanical and Electrical for Labs on west side.
            • Working on Level 6 Drywall, Ceilings, Mechanical and Electrical.
            • Working on Level 7 framing walls, Mechanical and Electrical.
          • Week of 11.18.19
            • Heritage
              • Steel Erection heavy equipment on site.
            • Wittson
              • Continuing work on Level 3 conference room, restroom  – Ceilings/Flooring
              • Level 3 Hospitalist project wall drywall on Level 3 South Side.
              • Class Lab 3020 Mechanical and Electrical Rough in.
              • Level 4 offices @ auditorium – Ceilings/Flooring
              • Level 4 installation of Mechanical and Electrical for Labs on west side.
              • Working on Level 6 Drywall, Ceilings, Mechanical and Electrical.
              • Working on Level 7 framing walls, Mechanical and Electrical.

 

Milestone Dates:

November 1: Level 2 Comparative Med will move out of storage rooms to allow plumbing for new Level 3 restroom.

November 4 through 17: Level 2 work in comp med storage rooms for plumbing to new Level 3 restroom.

May 6, 2020: MLS Lab/Classroom 3020 needs to be up and running.

Jan 19, 2021: Go Live of entire project.