Quick update on the Sorrell Courtyard project that coincides with the Exterior Façade work:
- Sidewalk and patio project (weather permitting)
- Lower patio center area is scheduled for a concrete pour tomorrow, Friday
- The sidewalk between the 2 sets of stairs on the North side of the patio is scheduled for a concrete pour on Tuesday
- This will remain closed through Wednesday – please use the ramp to the South per the construction tape and signs when accessing the South doors
- The piece of sidewalk leading up to the dock area and the ice rink is getting a trench drain and new concrete – this area will be poured once the boom-style lift is removed which should be next week
Phase 1 – Update:
- Demo activities are winding down
- 1 hour – Natural gas shut-down planned (gas outlets for burners inside lab)
- Abatement of flooring in progress – no impact outside of the construction area
- “Building sweat” seems to be under control since recent modifications were made
- An active water line was cut this week in error – UNMC responded with an emergency water shut-down while repairs were completed
- The reports I received indicated no impact outside of the construction zone
- New Construction:
- Metal stud framing starts week of 9/2
- Fume Hood removal and re-balancing
- Phase 1 fume hood disconnection is scheduled for 9/5
- CRA scheduled for 9/3 at 1030am
- Phase 1 fume hood disconnection is scheduled for 9/5
- Fire system shut-down by floor is complete.
- Exterior Work on South Façade:
- Area 1 is behind schedule. Painting is in progress and should be done Friday, 8/30
- The boom-style lift will be removed next week
- Shift to Area 2 (see image below) to follow
- Schedule & Budget:
- Phase 1 anticipated completion April of 2020
- No concerns at this time for either