July construction timeline update

  • Week of 7-1-19
    • Starting Construction work on level 4 offices at back side of auditorium
    • Continuing Level 8 construction work for divider wall, access, egress, life safety. Creation of North storage space.
    • Continuing construction work on Level 3 conference room, bike storage etc. at east wall of auditorium (inside auditorium)
    • Interior work for demolition of connector structure Temp window installation will occur on levels 6, 7, 8,
    • Continuing work from 6-24-19
  • Week of 7-8-19
    • Demolition starting on structural part of connector building between Wittson Hall and UT – heavy equipment on site.
    • Construction starts on restrooms on Level 2.
    • Continuing work from 7-1-19
  • Week of 7-15-19
    • Demolition continuing on structural part of connector building between Wittson Hall and UT– heavy equipment on site.
    • Continuing work from 7-8-19
    • Abatement work on L8 North (1.5-2 week duration)
  • Week of 7-22-19
    • Continuing work from 7-15-19
    • Moving Library materials equipment to L8 North
  • Week of 7-29-19
    • Foundation work and Pilings for new Heritage Center – heavy equipment on site.