Central Campus Construction

Wittson/Wigton Heritage Center updated schedule

  • Week of 6-17-19
    • Temp walkways will be installed on south side of jobsite
    • Interior work for demolition of connector structure (dock closed 6-18)
    • Continuing construction work on Level 3 conference room, bike storage etc. at east wall of auditorium (inside auditorium)
    • Starting Level 8 construction work for divider wall, access, egress, life safety. Creation of North storage space.
    • Starting demolition of connector structure 6-18(Dock closed)
    • Continuing work on Level 3 conference and Level 8 storage
  • Week of 6-24-19
    • Construction Crane will be delivered.
    • Scaffolding erected from Level 5 to Level 8
    • Construction work on level 4 offices at back side of auditorium
    • Continuing work started 6-17-19
  • Week of 7-1-19
    • Temp window installation will occur on levels 6, 7, 8,
    • Continuing work from 6-24-19
  • Week of 7-8-19
    • Construction starts on restrooms on Level 2.
    • Continuing work from 7-1-19
  • Week of 7-15-19
    • Continuing work from 7-8-19

Leave a Reply