Central Campus Construction
- Week of 5-27-19
- Temporary Fencing
- Site Signage
- Wayfinding signs will be installed
- Week of 6-3-19
- Construction office will be delivered.
- Construction Crane will be delivered.
- Scaffolding erected from Level 5 to Level 8
- Temporary construction walls will be
- Work for demolition of connector structure (dock closed)
- Starting work on small restroom renovation on level 2.
- Starting construction work on Level 3 conference room, bike storage etc. at east wall of auditorium (inside auditorium)
- Starting Level 8 construction work for divider wall, access, egress, life safety. Creation of North storage space.
- Week of 6-10-19
- Window work will occur on levels 6, 7, 8
- Work for demolition of connector structure
- Continuing work on Level 3 conference and Level 8 storage
- Construction work on Heritage Center
- Week of 6-17-2019
- Work on level 4 offices at back side of auditorium
- Continuing work on Level 3 conference and Level 8 storage
- Construction work on Heritage Center