  • Week of 5-27-19
    • Temporary Fencing
    • Site Signage
    • Wayfinding signs will be installed
  • Week of 6-3-19
    • Construction office will be delivered.
    • Construction Crane will be delivered.
    • Scaffolding erected from Level 5 to Level 8
    • Temporary construction walls will be
    • Work for demolition of connector structure (dock closed)
    • Starting work on small restroom renovation on level 2.
    • Starting construction work on Level 3 conference room, bike storage etc. at east wall of auditorium (inside auditorium)
    • Starting Level 8 construction work for divider wall, access, egress, life safety. Creation of North storage space.
  • Week of 6-10-19
    • Window work will occur on levels 6, 7, 8
    • Work for demolition of connector structure
    • Continuing work on Level 3 conference and Level 8 storage
    • Construction work on Heritage Center
  • Week of 6-17-2019
    • Work on level 4 offices at back side of auditorium
    • Continuing work on Level 3 conference and Level 8 storage
    • Construction work on Heritage Center