Facilities Briefs

LIED TRANSPLANT CENTER (LTC)

DOMESTIC HOT WATER SHUTDOWN

On Monday, February 16, 2015, the domestic hot water will be turned off in the Lied Transplant Center (LTC) building.  This shutdown will affect the hot water to all the bathrooms, kitchens and labs on levels 8 through 12.

This shutdown of the domestic hot water is for the repair of the hot water heater.

Shutdown Schedule:

Start Time:   Monday, February 16, 2015, at 6:00 a.m.
End Time:    Monday, February 16, 2015, at 2:00 p.m. (Approximately)

If you have any questions, please contact James Weiss at 402-290-7196 or by email at jlweiss@unmc.edu.

EPPLEY SCIENCE HALL – LEVELS 5 and 6

Level 6 Utilities – Shutdown
Level 5 – Contractor Access to Rooms/Areas

The construction company, AOI Corporation along with Facilities Management and Planning have scheduled a shutdown to ESH Level 6.  This will affect services to the south labs.  The work will occur on Saturday, February 14, 2015, from 7:00am until 7:00pm.  To do this work, the Contractor will need to shutdown the radiant heat on the south side of ESH.  The work will also require the shutdown of all lab gases, including air, gas and vacuum. The RO water system for the entire ESH building will be turned off during this time.  The Domestic water will be turned off for 2 hours on Level 5 and 6 only.

The contractor will need to access the south area of level 5:

Areas:
Corridor 5099B                  Lab 5007                Surgery 5006
Corridor 5099A                  Lab 5004                Proc/Cage 5003
Corridor 5099C                 Office/Fume 5005

If you have any questions or concerns, please call Nick Knopik at 402-350-2067.  (click on photo to enlarge)

Eppley Science Hall - Level 5

STUDENT LIFE CENTER (SLC)

STEAM SHUT-DOWN

On Tuesday, February 10, 2015, there will be a steam shut-down to the Student Life Center on all levels. This interruption will affect the heat in the building and domestic hot water to all kitchens, labs and bathrooms.

This shut-down is for the purpose of replacing a crack fitting on the steam line.

Shut-down Schedule:
Start Time: Tuesday, February 10, 2015, at 6:00 p.m.
End Time: Tuesday, February 10, 2015, at 8:00 p.m. (Approximately)

If you have any questions, please contact me (Terry Vail) at 402-559-6342 or tvail@unmc.edu. Since it is vital that everyone working in the SLC building be aware, I ask that you mention this shut-down to your colleagues.