Facilities Briefs

TRUHLSEN EYE INSTITUTE ELECTRICAL POWER INTERRUPTION – UPDATE!

On Thursday,  August  28, 2014, there will be an extended interruption (shut off) of emergency electrical power that serves all levels of the UNMC Truhlsen Eye Institute. During this time, emergency power will be disconnected and only items connected to the normal power supply will remain energized. This will cause an extended outage to all “RED” receptacle outlets, lighting, air handling units, supply fans, exhaust fans, fume hoods, motors, etc.

This outage is needed to complete repairs done on an Automatic Transfer Switch, (ATS).

Interruption Schedule:

Start Time:         Thursday August  28, 2014, @  7:00 p.m. (1900 hrs)

End Time:          Thursday August  28, 2014, @ 9:00 p.m. (2100 hrs)                               (Approximately)

If you have any questions, please contact  Matt Monaghan at ext. 402-559-7188.  Since it is vital that everyone working in the affected areas be advised of this, please mention this electrical power interruption to your colleagues.

 

Leave a Reply


3 × five =